Final | 7/11/2000 | 7/11/2000 | 7/11/2000 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 07/11/2000 at 07:48:33. Contact: ###-####.
|
Final | 6/27/2000 | 6/28/2000 | 6/28/2000 | A | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 06/27/2000 at 09:40:28. Contact: ###-####.
|
Electrical Rough-In | 5/8/2000 | 5/8/2000 | 5/8/2000 | P | PASS |
Joe Ray
|
|
|
###-#### pool lights
|
Electrical Rough-In | 4/14/2000 | 4/14/2000 | 4/14/2000 | P | FAIL |
Joe Ray
|
|
|
rowdy--###-####--unground insp Trench covered could not see 4/17/00 9:24:48 AM
|
Electrical Rough-In | 3/22/2000 | 3/22/2000 | 3/22/2000 | P | PART |
Jack Frank
|
|
|
###-#### bonding Pool bond ok note is U/G to well pump within 5 ft. of pool called left message waiting for answer. 3/23/00 9:01:31 AM
|