Final | 10/13/2000 | 10/13/2000 | 10/13/2000 | P | PASS |
Marv Burrus
|
|
|
FN -- SARA ###-#### . COMPLETED. 10/15/2000 8:45:18 PM
|
Final | 10/5/2000 | 10/5/2000 | 10/5/2000 | P | PART |
Mike Kinnear
|
|
|
temp occ Sara ###-#### TEMP OCC OK 10/5/2000 5:09:18 PM
|
Final | 9/27/2000 | 9/28/2000 | 9/28/2000 | A | PART |
Marv Burrus
|
|
|
partial final Brad ###-####. roof-top hvac units
r/i, ceiling above kitchen area r/i. 9/28/2000 10:27:47 PM
|
Rough-In Permanent Service | 9/7/2000 | 9/7/2000 | 9/7/2000 | A | PART |
Marv Burrus
|
|
|
###-#### George . 5 sub-panels in mezanine area. 9/10/2000 6:01:50 PM
|
Electrical Rough-In | 8/24/2000 | 8/25/2000 | 8/25/2000 | A | PASS |
Jim Schmer
|
|
|
Scheduled by a contractor via Hello! on 08/24/2000 at 11:34:22. Contact: ###-####. bathrooms & back wall of kitchen r/i - ok 8/25/2000 5:03:35 PM
|
Electrical Rough-In | 8/11/2000 | 8/14/2000 | 8/14/2000 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 08/11/2000 at 15:57:55. Contact: ###-####. walls ele r/i. pit, front and middle areas. 8/14/2000 12:40:32 PM
|
Electrical Rough-In | 7/19/2000 | 7/19/2000 | 7/19/2000 | P | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 07/19/2000 at 09:30:21. Contact: ###-####. Ok cover conduit in slab 7/20/00 9:34:17 AM
|
Electrical Rough-In | 7/12/2000 | 7/13/2000 | 7/13/2000 | A | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 07/12/2000 at 17:08:21. Contact: ###-####. Ok cover pool fixture 7/14/00 9:00:37 AM
|