Final | 3/18/2002 | 3/19/2002 | 3/19/2002 | A | PASS |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 03/18/2002 at 18:56:04. Contact: ###-####.
|
Final | 3/14/2002 | 3/15/2002 | 3/15/2002 | A | PART |
Jack Frank
|
|
|
###-#### -curtis fn conference only see JF for details ENT in pole to seperate coax and power wiring 3/15/2002 11:23:58 AM
|
Final | 3/12/2002 | 3/12/2002 | 3/12/2002 | P | FAIL |
Pat Lass
|
|
|
###-#### call first to meet there roof top receps and coax in with line voltage in poles 3/12/2002 4:28:55 PM
|
Final | 2/14/2002 | 2/14/2002 | 2/14/2002 | P | PART |
Pat Lass
|
|
|
Scheduled by Inspector: 336 On 2/14/2002 10:02:44 AM signed T/O some things not finished pole lites under floor to desks furnature 2/14/2002 6:01:10 PM
|
Final | 2/13/2002 | 2/13/2002 | 2/13/2002 | P | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 02/13/2002 at 08:36:31. Contact: ###-####.
|
Final | 2/13/2002 | 2/13/2002 | 2/13/2002 | P | CANC |
Pat Lass
|
|
|
fn ###-#### fn --curtis wrong date 2/14/2002 10:03:15 AM
|
Electrical Rough-In | 1/31/2002 | 2/4/2002 | 2/4/2002 | A | NR |
Pat Lass
|
|
|
CURTIS ###-####
|
Electrical Rough-In | 1/31/2002 | 2/4/2002 | 2/4/2002 | P | PART |
Pat Lass
|
|
|
CURTIS ###-####
|
Electrical Rough-In | 1/21/2002 | 1/22/2002 | 1/22/2002 | P | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 01/21/2002 at 15:46:14. Contact: ###-####. Partial ceiling R/I 1/22/2002 3:51:59 PM
|
Electrical Rough-In | 1/14/2002 | 1/15/2002 | 1/15/2002 | P | PART |
Pat Lass
|
|
|
Scheduled by Inspector: 336 On 1/14/2002 12:15:40 PM
|
Electrical Rough-In | 1/11/2002 | 1/13/2002 | 1/13/2002 | P | NR |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 01/11/2002 at 07:52:38. Contact: ###-####.
|
Electrical Rough-In | 12/18/2001 | 12/19/2001 | 12/19/2001 | A | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 12/18/2001 at 15:29:26. Contact: ###-####.
|
Electrical Rough-In | 12/10/2001 | 12/11/2001 | 12/11/2001 | A | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 12/10/2001 at 13:07:43. Contact: ###-####. walls ok 12/11/2001 10:02:14 AM
|
Electrical Rough-In | 12/5/2001 | 12/5/2001 | 12/5/2001 | P | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 12/05/2001 at 09:02:46. Contact: ###-####.
|
Rough-In Permanent Service | 11/30/2001 | 12/3/2001 | 12/3/2001 | A | PASS |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 11/30/2001 at 08:46:52. Contact: ###-####. P/S U/G N Ok 12/3/2001 10:29:32 AM
|
Electrical Rough-In | 11/26/2001 | 11/27/2001 | 11/27/2001 | A | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 11/26/2001 at 10:54:08. Contact: ###-####. Mid section walls ok 11/27/2001 10:53:07 AM
|
Electrical Rough-In | 11/9/2001 | 11/13/2001 | 11/13/2001 | A | PART |
Pat Lass
|
|
|
N/E wallsok 11/13/2001 12:32:59 PM
|
Electrical Rough-In | 10/29/2001 | 11/1/2001 | 11/1/2001 | P | PART |
Pat Lass
|
|
|
###-#### ###-####North walls 11/1/2001 4:23:49 PM
|
ELE-Aging Inspection | 10/29/2001 | 10/29/2001 | 10/29/2001 | | NR |
Pat Lass
|
|
|
SUC 10/29/2001 12:36:21 PM
|
ELE-Aging Inspection | 8/29/2001 | 8/29/2001 | 8/29/2001 | | NR |
Pat Lass
|
|
|
SUC 8/29/2001 8:26:50 AM
|
Electrical Rough-In | 6/29/2001 | 6/29/2001 | 6/29/2001 | P | PASS |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 06/29/2001 at 08:34:02. Contact: ###-####.
|
Electrical Rough-In | 6/19/2001 | 6/20/2001 | 6/20/2001 | P | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 06/19/2001 at 11:49:35. Contact: ###-####.
|
Electrical Rough-In | 6/15/2001 | 6/18/2001 | 6/18/2001 | A | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 06/15/2001 at 16:07:59. Contact: ###-####.
|
Electrical Rough-In | 6/8/2001 | 6/8/2001 | 6/8/2001 | P | PART |
Pat Lass
|
|
|
###-####
|
Electrical Rough-In | 6/5/2001 | 6/6/2001 | 6/6/2001 | P | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 06/05/2001 at 12:00:46. Contact: ###-####.
|
Electrical Rough-In | 5/23/2001 | 5/24/2001 | 5/24/2001 | A | PASS |
Pat Lass
|
|
|
underground ###-####
|