Final | 2/28/2002 | 3/1/2002 | 3/1/2002 | P | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 02/28/2002 at 14:15:05. Contact: ###-####. tennant improvement 1st and 2nd floor, complete. 3/1/2002 2:41:40 PM
|
Final | 2/9/2002 | 2/11/2002 | 2/11/2002 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 02/09/2002 at 07:07:49. Contact: ###-####. 2nd floor: nicu east tower expansion, temporary occupancy only. 2/11/2002 11:17:50 AM
|
Final | 2/7/2002 | 2/8/2002 | 2/8/2002 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 02/07/2002 at 17:57:47. Contact: ###-####. 1st floor: emergency dept., new wing. temporary occupancy only. 2/8/2002 12:48:02 PM
|
Electrical Rough-In | 1/29/2002 | 1/30/2002 | 1/30/2002 | P | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 01/29/2002 at 13:32:11. Contact: ###-####. 1st floor ceiling r/i. 1/30/2002 2:17:32 PM
|
Electrical Rough-In | 1/21/2002 | 1/22/2002 | 1/22/2002 | A | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 01/21/2002 at 16:42:57. Contact: ###-####. 1st floor; 2-x-ray rooms, and 2 nurses. 1/22/2002 11:40:48 AM
|
Electrical Rough-In | 1/15/2002 | 1/16/2002 | 1/16/2002 | A | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 01/15/2002 at 11:41:48. Contact: ###-####. elevator lobby's, 3rd and 4th floor r/i. 1/16/2002 10:44:30 AM
|
Electrical Rough-In | 1/9/2002 | 1/10/2002 | 1/10/2002 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 01/09/2002 at 11:39:56. Contact: ###-####. 1st floor nurses staions, (2); 2nd floor; equiptment rooms, isolation room. 1/10/2002 11:27:04 AM
|
Electrical Rough-In | 12/17/2001 | 12/18/2001 | 12/18/2001 | A | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 12/17/2001 at 08:48:20. Contact: ###-####. 2nd floor; n.i.c.u. rooms(2), transition rooms (3) walls r/i; corridor soffit recessed lights r/i. 12/18/2001 11:11:17 AM
|
Electrical Rough-In | 11/30/2001 | 12/3/2001 | 12/3/2001 | A | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 11/30/2001 at 08:50:48. Contact: ###-####. stairwell #10; ceiling r/i basemnt thru 2nd floor. 1st and 2nd floor elevator columns r/. 12/3/2001 9:01:19 AM
|
Electrical Rough-In | 11/16/2001 | 11/19/2001 | 11/19/2001 | A | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 11/16/2001 at 15:36:29. Contact: ###-####. 1st floor; 2-bathrooms, shower room ceiling r/i. 11/19/2001 8:50:23 AM
|
Electrical Rough-In | 11/6/2001 | 11/7/2001 | 11/7/2001 | P | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 11/06/2001 at 13:43:51. Contact: ###-####. 1st. floor; elevator walls r/i; 2nd floor, elevator walls and soffit r/i, ok. 11/7/2001 3:07:07 PM
|
Electrical Rough-In | 10/25/2001 | 10/26/2001 | 10/26/2001 | P | PASS |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 10/25/2001 at 12:02:35. Contact: ###-####. stairtowers; fire-alarms sub-basement thru 5th floor r/i. 10/26/2001 2:02:32 PM
|
Electrical Rough-In | 10/19/2001 | 10/22/2001 | 10/22/2001 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 10/19/2001 at 13:40:42. Contact: ###-####. 2nd floor walls r/i which are marked on prints. 10/22/2001 3:24:57 PM
|
Electrical Rough-In | 10/1/2001 | 10/3/2001 | 10/3/2001 | A | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 10/01/2001 at 13:21:49. Contact: ###-####. ok cover walls 2nd floor that is marked on print 10/3/2001 1:31:52 PM
|
Electrical Rough-In | 9/19/2001 | 9/20/2001 | 9/20/2001 | P | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 09/19/2001 at 08:33:58. Contact: ###-####. 1st floor; interior soffit recessed lighting r/i, ok. 9/20/2001 2:53:00 PM
|
Electrical Rough-In | 9/11/2001 | 9/13/2001 | 9/13/2001 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 09/11/2001 at 08:48:03. Contact: ###-####. 1st floor; barhrooms, exam rooms, patient care rooms r/i. 9/13/2001 9:59:08 AM
|
Electrical Rough-In | 8/22/2001 | 8/24/2001 | 8/24/2001 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 08/22/2001 at 14:55:31. Contact: .
1st floor: exam rooms, bathrooms, nurse-call station r/i.
8/24/2001 10:11:30 AM
|
Electrical Rough-In | 7/25/2001 | 7/26/2001 | 7/26/2001 | P | PASS |
Jim Schmer
|
|
|
Scheduled by a contractor via Hello! on 07/25/2001 at 09:18:45. Contact: ###-####.
|
ELE-Aging Inspection | 7/24/2001 | 7/24/2001 | 7/24/2001 | | PASS |
Marv Burrus
|
|
|
still in progress 7/24/2001 7:46:37 AM
|
Electrical Rough-In | 5/23/2001 | 5/24/2001 | 5/24/2001 | A | PART |
Marv Burrus
|
|
|
Scheduled by a contractor via Hello! on 05/23/2001 at 12:01:01. Contact: .
dennis: ###-####. conference; mounting of j-boxes and gutters. 5/24/2001 8:50:45 AM
|