ELE-Aging Inspection | 9/4/2003 | 9/4/2003 | 9/4/2003 | | PART |
Jack Frank
|
|
|
WSUC 9/10/2003 2:30:54 PM
|
Electrical Rough-In | 7/1/2003 | 7/1/2003 | 7/1/2003 | P | PASS |
Jack Frank
|
|
|
xformer for rental car trailers
|
Electrical Rough-In | 6/24/2003 | 6/24/2003 | 6/24/2003 | P | PART |
Jack Frank
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Barbara Moore u/G and electrode ok 6/24/2003 2:42:37 PM
|
Final | 6/13/2003 | 6/13/2003 | 6/13/2003 | P | PART |
Jack Frank
|
|
|
temp occupancy ok for phase one all floors
|
Final | 6/12/2003 | 6/12/2003 | 6/12/2003 | P | PART |
Jack Frank
|
|
|
01 with Lea
|
Final | 6/4/2003 | 6/5/2003 | 6/5/2003 | A | PART |
Jack Frank
|
|
|
meeting with dennis temp ok for 1st, 2nd floor baggage, and ticket areas 6/5/2003 9:19:51 AM
|
Final | 6/4/2003 | 6/5/2003 | 6/5/2003 | P | PART |
Jack Frank
|
|
|
generator test will be rescheduled Lea ok , but control tec and phone need to complete corrections 6/5/2003 3:28:53 PM
|
Electrical Rough-In | 5/29/2003 | 5/29/2003 | 5/29/2003 | P | PART |
Jack Frank
|
|
|
walls 2nd floor office ok 5/29/2003 12:41:09 PM
|
Final | 5/22/2003 | 5/27/2003 | 5/27/2003 | A | CANC |
Jack Frank
|
|
|
meet with Monty of control tec
|
Final | 5/27/2003 | 5/27/2003 | 5/27/2003 | A | PART |
Jack Frank
|
|
|
final basement temp only 5/27/2003 12:17:03 PM
|
Final | 5/21/2003 | 5/22/2003 | 5/22/2003 | A | PART |
Jack Frank
|
|
|
conveyor wiring 5/22/2003 4:04:01 PM
|
Electrical Rough-In | 5/21/2003 | 5/21/2003 | 5/21/2003 | A | PART |
Jack Frank
|
|
|
r/i for check in counters
|
Final | 5/21/2003 | 5/21/2003 | 5/21/2003 | A | PART |
Mike Kinnear
|
|
|
ok part final area i looked at
|
Final | 5/20/2003 | 5/21/2003 | 5/21/2003 | A | PART |
Jack Frank
|
|
|
temp for 2nd floor east half 5/21/2003 10:59:21 AM
|
Final | 5/21/2003 | 5/21/2003 | 5/21/2003 | P | PART |
Jack Frank
|
|
|
temp 2nd floor ok except west end , and main lobby check in area 5/21/2003 4:24:46 PM
|
Final | 5/19/2003 | 5/19/2003 | 5/19/2003 | A | PART |
Jack Frank
|
|
|
temp for 3rd floor 5/19/2003 10:43:30 AM
|
Final | 5/19/2003 | 5/19/2003 | 5/19/2003 | A | PART |
Jack Frank
|
|
|
3rd floor temp 2 electrical rms ,mech. rm, and offices print marked 5/19/2003 1:11:45 PM
|
Electrical Rough-In | 4/3/2003 | 4/3/2003 | 4/3/2003 | A | PART |
Jack Frank
|
|
|
r/i 3rd floor ceiling ok, the part final was a mistake
|
Final | 4/3/2003 | 4/3/2003 | 4/3/2003 | A | PART |
Jack Frank
|
|
|
3rd floor ceilings ok
|
Electrical Rough-In | 3/28/2003 | 3/28/2003 | 3/28/2003 | P | PART |
Jack Frank
|
|
|
ceiling ok
|
Electrical Rough-In | 2/18/2003 | 2/18/2003 | 2/18/2003 | P | PART |
Jack Frank
|
|
|
area b west and partial ceiling walkway
|
Electrical Rough-In | 2/7/2003 | 2/7/2003 | 2/7/2003 | P | PART |
Jack Frank
|
|
|
area B east, and 2nd floor rotunda area ceilings and soffits 2/7/2003 2:54:24 PM
|
Electrical Rough-In | 1/21/2003 | 1/21/2003 | 1/21/2003 | P | PART |
Jack Frank
|
|
|
3rd floor east end north side 3 rms
|
Electrical Rough-In | 1/16/2003 | 1/16/2003 | 1/16/2003 | P | PART |
Jack Frank
|
|
|
3rd floor south side , andN. E. end of corridor
|
Electrical Rough-In | 1/8/2003 | 1/9/2003 | 1/9/2003 | A | PART |
Jack Frank
|
|
|
am r/i for Lea elect 1st floor area A-.8 and 3rd floor area C ceiling 1/9/2003 12:45:31 PM
|
Final | 12/16/2002 | 12/17/2002 | 12/17/2002 | P | PART |
Jack Frank
|
|
|
MIKE ###-#### TEMP WALK WAY temp occupancy only for walkway card signed by JF, and JS 12/17/2002 4:20:55 PM
|
Electrical Rough-In | 12/13/2002 | 12/13/2002 | 12/13/2002 | P | PART |
Jack Frank
|
|
|
CEILING INSP----###-#### VICKY ok for walk way , and walls 2nd floor of terminal 12/13/2002 5:47:51 PM
|
Electrical Rough-In | 12/10/2002 | 12/10/2002 | 12/10/2002 | P | PART |
Jack Frank
|
|
|
r/i area (C) car rental walls ok
|
Electrical Rough-In | 12/3/2002 | 12/3/2002 | 12/3/2002 | P | PART |
Jack Frank
|
|
|
r/i for 3rd floor rotunda ceiling ok 12/3/2002 6:18:08 PM
|
Electrical Rough-In | 12/3/2002 | 12/3/2002 | 12/3/2002 | P | PART |
Jack Frank
|
|
|
conference ok met with Dan of Arco electric
|
Electrical Rough-In | 11/18/2002 | 11/18/2002 | 11/18/2002 | P | PART |
Jack Frank
|
|
|
2nd floor E&W of center north corridor and 1st floor area C 11/18/2002 6:28:31 PM
|
Electrical Rough-In | 11/8/2002 | 11/8/2002 | 11/8/2002 | A | PART |
Jack Frank
|
|
|
2nd floor north side of corridor west end
|
Electrical Rough-In | 10/24/2002 | 10/24/2002 | 10/24/2002 | P | PART |
Jack Frank
|
|
|
temp walkway ok
|
Electrical Rough-In | 10/23/2002 | 10/23/2002 | 10/23/2002 | A | PART |
Jack Frank
|
|
|
walls south central 2nd floor boat #4 and rotunda 1st floor
|
Electrical Rough-In | 10/18/2002 | 10/18/2002 | 10/18/2002 | P | PART |
Jack Frank
|
|
|
r/i and conference cooling towers airport met with Lea electric
|
Final | 10/14/2002 | 10/14/2002 | 10/14/2002 | A | PART |
Jack Frank
|
|
|
final for new restroom concourse (A)
|
Electrical Rough-In | 10/7/2002 | 10/8/2002 | 10/8/2002 | A | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 10/07/2002 at 07:42:05. Contact: ###-####. r/i ok for boats 1,2,and3 in area A, and partial soffits in rotundra
10/8/2002 12:15:46 PM
|
Electrical Rough-In | 10/8/2002 | 10/8/2002 | 10/8/2002 | P | PART |
Jack Frank
|
|
|
ok conference 10/8/2002 6:52:09 PM
|
Electrical Rough-In | 9/23/2002 | 9/23/2002 | 9/23/2002 | P | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 09/23/2002 at 10:42:19. Contact: . 1st and 2nd floor restrms 9/23/2002 4:50:09 PM
|
Electrical Rough-In | 9/13/2002 | 9/16/2002 | 9/16/2002 | A | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 09/13/2002 at 12:40:45. Contact: ###-####.bath rms floors 2and 3, walls 1st floor 9/16/2002 11:43:38 AM
|
Rough-In Permanent Service | 8/30/2002 | 9/3/2002 | 9/3/2002 | A | PASS |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 08/30/2002 at 08:28:08. Contact: ###-####.
p/s u/g new ok 9/3/2002 12:09:29 PM
|
Electrical Rough-In | 7/25/2002 | 7/26/2002 | 7/26/2002 | P | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 07/25/2002 at 14:48:11. Contact: ###-####. u/g for parking lot lights 7/26/2002 3:37:03 PM
|
Electrical Rough-In | 7/19/2002 | 7/22/2002 | 7/22/2002 | A | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 07/19/2002 at 15:10:23. Contact: ###-####. r/i for temp walkway 7/22/2002 11:46:13 AM
|
Electrical Rough-In | 7/3/2002 | 7/3/2002 | 7/3/2002 | P | PART |
Jack Frank
|
|
|
conference ok met Dennis clearence in electrical rm
|
Electrical Rough-In | 6/21/2002 | 6/21/2002 | 6/21/2002 | P | PART |
Jack Frank
|
|
|
u/g for generator ok
|
Electrical Rough-In | 6/10/2002 | 6/10/2002 | 6/10/2002 | P | PART |
Jack Frank
|
|
|
concrete encased electrode ok
|
Electrical Rough-In | 4/22/2002 | 4/22/2002 | 4/22/2002 | P | PART |
Jack Frank
|
|
|
Added by Inspector: 315 On 4/22/2002 3:59:39 PM conference met with Dennis, he had a question about clearences in basement
|
Electrical Rough-In | 4/18/2002 | 4/19/2002 | 4/19/2002 | A | PART |
Jack Frank
|
|
|
dennis ###-#### r/i --underground ok 4/19/2002 11:56:40 AM
|
Electrical Rough-In | 4/11/2002 | 4/12/2002 | 4/12/2002 | A | PART |
Jack Frank
|
|
|
Scheduled by Inspector: 315 On 4/11/2002 4:43:41 PM conference with Dennis ok r/i ok for basement 4/12/2002 12:16:13 PM
|
Electrical Rough-In | 4/11/2002 | 4/11/2002 | 4/11/2002 | P | CANC |
Jack Frank
|
|
|
DENNIS ###-#### WALL R/I BACEMENT talked with contractor 4/11/2002 4:54:40 PM
|
ELE-Aging Inspection | 1/21/2002 | 1/21/2002 | 1/21/2002 | | PART |
Jack Frank
|
|
|
W S U C 1/23/2002 10:46:00 AM
|
Electrical Rough-In | 11/19/2001 | 11/20/2001 | 11/20/2001 | P | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 11/19/2001 at 16:19:16. Contact: ###-####. u/g duct bank basement 11/20/2001 10:51:06 AM
|
Electrical Rough-In | 11/7/2001 | 11/8/2001 | 11/8/2001 | A | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 11/07/2001 at 15:57:12. Contact: ###-####. u/g basement 11/8/2001 11:07:03 AM
|
Electrical Rough-In | 11/2/2001 | 11/5/2001 | 11/5/2001 | A | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 11/02/2001 at 14:42:12. Contact: ###-####. part. u/g basement of new terminal 11/5/2001 1:02:48 PM
|