Final | 4/9/2002 | 4/10/2002 | 4/10/2002 | A | PASS |
Marv Burrus
|
|
|
CALL BILL THOMAS ###-#### FOR ACCESS
|
Rough-In Permanent Service | 3/6/2002 | 3/6/2002 | 3/6/2002 | P | PASS |
Marv Burrus
|
|
|
###-#### BILL KEY IS IN BOTTOM MAIN DISCONNECT. corrections completed.
p/s ug new challenger ele #3860-ok
pump station. 3/6/2002 2:21:33 PM
|
Permanent Service | 3/1/2002 | 3/4/2002 | 3/4/2002 | A | FAIL |
Marv Burrus
|
|
|
###-#### BILL KEY AT BOTTOM OF MAIN DISCONNECT nec: 250. equiptment bonding required. 110-26: clearances in front of disconnect. lock-nuts not approved for damp locations. discussed violations with contractor. idaho power connected to power before inspection.. 3/4/2002 11:02:29 AM
|
Electrical Rough-In | 2/25/2002 | 2/28/2002 | 2/28/2002 | A | CANC |
Marv Burrus
|
|
|
###-####. contractors request, will reschedule. 2/27/2002 4:20:47 PM
|
Electrical Rough-In | 12/18/2001 | 12/18/2001 | 12/18/2001 | P | PASS |
Marv Burrus
|
|
|
BILL ###-####. pvc conduit under-slab. pump station. 12/18/2001 2:48:31 PM
|
Electrical Rough-In | 12/13/2001 | 12/13/2001 | 12/13/2001 | P | PASS |
Marv Burrus
|
|
|
UFER\\\###-#### BILL. ufer grounding conductor. ok. 12/13/2001 2:01:28 PM
|
Electrical Rough-In | 11/27/2001 | 11/27/2001 | 11/27/2001 | P | PASS |
Marv Burrus
|
|
|
###-#### TOM ###-####. pvc conduit in pump station upper decking, ok for concrete pour. 11/27/2001 2:19:48 PM
|