Electrical Rough-In | 10/10/2002 | 10/10/2002 | 10/10/2002 | P | CANC |
Mike Kinnear
|
|
|
Phone #: ###-#### Internet Inspection Request from: Amy Lawson wrong type inspection 10/10/2002 3:33:50 PM
|
Final | 10/10/2002 | 10/10/2002 | 10/10/2002 | P | PASS |
Mike Kinnear
|
|
|
ok final
|
Final | 10/1/2002 | 10/2/2002 | 10/2/2002 | A | PART |
Mike Kinnear
|
|
|
renee ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie part final peluim over clean rm ok 10/2/2002 11:26:45 AM
|
Final | 9/23/2002 | 9/23/2002 | 9/23/2002 | P | PART |
Mike Kinnear
|
|
|
RENEE; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok final areas sub fab rm003B, scrubber rm001I, scrubber fan deck, corridors 3rd floor, mech rm 3rd floor,& litho support rm109B 9/23/2002 6:45:27 PM
|
Final | 9/3/2002 | 9/4/2002 | 9/4/2002 | A | DONE |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 09/03/2002 at 11:55:55. Contact: ###-####. called no inspection needed 9/4/2002 1:51:05 PM
|
Final | 8/30/2002 | 9/3/2002 | 9/3/2002 | P | PART |
Jack Frank
|
|
|
RENE; Phone #: ###-#### Internet Inspection Request from: Darla Downs needs to bond exposed metel conduit at pole, interiorpiping bonding ok 9/3/2002 6:17:05 PM
|
Final | 8/23/2002 | 8/23/2002 | 8/23/2002 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 08/23/2002 at 07:58:06. Contact: ###-####. part final rooms 101P, 101W, 101L, 110A, 112B, 1112A, 1101H, 101I, scrubber fan deck, 106B, 101C, 109A, 002A, 001B, 001C, 001D, 001E, 001H, 001G, 002B, 101N 8/23/2002 3:19:55 PM
|
Final | 8/1/2002 | 8/5/2002 | 8/5/2002 | A | NR |
Mike Kinnear
|
|
|
RENE; Phone #: ###-#### not ready 8/5/2002 9:41:28 AM
|
Final | 7/29/2002 | 7/30/2002 | 7/30/2002 | A | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 07/29/2002 at 11:35:02. Contact: ###-####. ok part finalplenium southside, mech rm 101D, stairs 1,2,3, office area all, venders rm cori. adj. office, batrms 101UV, janitor rm 101M, fmcs rm 101R, stairs 4,5,6. 7/30/2002 9:46:58 AM
|
Final | 7/26/2002 | 7/26/2002 | 7/26/2002 | P | PART |
Mike Kinnear
|
|
|
per mike fn conf with dan 7/26/2002 4:46:29 PM
|
Final | 7/19/2002 | 7/19/2002 | 7/19/2002 | P | PART |
Mike Kinnear
|
|
|
rene; Phone #: ###-#### ok temp. occ. office area note lockouts for water cooler & insta h2o heaters-- spark rings for some wall switches & outlets 7/19/2002 5:05:24 PM
|
Final | 7/15/2002 | 7/15/2002 | 7/15/2002 | P | FAIL |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 07/15/2002 at 08:28:26. Contact: ###-####. correction NEC 400.8 part 7/15/2002 3:30:36 PM
|
Electrical Rough-In | 7/11/2002 | 7/12/2002 | 7/12/2002 | A | PART |
Mike Kinnear
|
|
|
TEMP FINAL RENE ###-#### ok cover part ceiling rms 104B & 104F CORIDOR 100D 7/12/2002 3:43:00 PM
|
Electrical Rough-In | 7/12/2002 | 7/12/2002 | 7/12/2002 | P | PART |
Mike Kinnear
|
|
|
R/I- RENE- ###-#### CELL ok cover part ceiling coridor 100B, ves.100A, rms 103B & 102A 7/12/2002 3:45:46 PM
|
Electrical Rough-In | 7/1/2002 | 7/2/2002 | 7/2/2002 | A | PART |
Mike Kinnear
|
|
|
RENE ###-#### pre inspection ceiling 7/2/2002 8:13:35 AM
|
Electrical Rough-In | 7/2/2002 | 7/2/2002 | 7/2/2002 | P | PART |
Mike Kinnear
|
|
|
RENE ###-#### CELING ok cover ceiling except for rms 104B & 104F 7/2/2002 3:37:50 PM 7/2/2002 3:38:24 PM
|
Electrical Rough-In | 6/27/2002 | 6/27/2002 | 6/27/2002 | P | PART |
Mike Kinnear
|
|
|
r/i- renee ###-#### ok pre final inspection 6/27/2002 12:20:59 PM
|
Electrical Rough-In | 6/20/2002 | 6/20/2002 | 6/20/2002 | P | PART |
Mike Kinnear
|
|
|
###-#### RENE ok cover walls locker room 6/20/2002 12:26:26 PM
|
Electrical Rough-In | 6/19/2002 | 6/19/2002 | 6/19/2002 | P | PASS |
Mike Kinnear
|
|
|
per mike r/i & conf ok conf. 6/19/2002 3:59:08 PM
|
Electrical Rough-In | 6/12/2002 | 6/12/2002 | 6/12/2002 | P | PART |
Mike Kinnear
|
|
|
RENE ###-#### ok cover bathroom ceilings 6/12/2002 1:17:16 PM
|
Electrical Rough-In | 6/4/2002 | 6/6/2002 | 6/6/2002 | A | CANC |
Mike Kinnear
|
|
|
rene ###-#### canc by contractor 6/6/2002 8:29:11 AM
|
Electrical Rough-In | 6/5/2002 | 6/5/2002 | 6/5/2002 | P | PASS |
Jim Schmer
|
|
|
r/i- rene- ###-#### -per rene give to jim 6/5/2002 12:11:46 PM
|
Electrical Rough-In | 6/4/2002 | 6/5/2002 | 6/5/2002 | A | CANC |
Mike Kinnear
|
|
|
RENE ###-#### t/w rene ok change inspection for 5/6/02 am 6/4/2002 5:43:17 PM
|
Electrical Rough-In | 5/30/2002 | 5/31/2002 | 5/31/2002 | A | PART |
Mike Kinnear
|
|
|
###-#### RENAE part ok cover ex wall s&w corner1st floor 5/31/2002 2:23:48 PM
|
Electrical Rough-In | 5/30/2002 | 5/30/2002 | 5/30/2002 | P | PART |
Mike Kinnear
|
|
|
wall r/i- renea- ###-#### part ok cover walls rms 104 H,I,J,K,&L rm 100Y&X 5/30/2002 3:01:38 PM
|
Rough-In Permanent Service | 5/16/2002 | 5/17/2002 | 5/17/2002 | A | PASS |
Jim Schmer
|
|
|
RENE ###-#### Looked at 3 mains for length and connection, 2 still need cond. pulled. Having 3 megged over weekend. 5/17/2002 9:16:47 AM
|
Rough-In Permanent Service | 5/10/2002 | 5/13/2002 | 5/13/2002 | A | FAIL |
Mike Kinnear
|
|
|
rene ###-#### transformers NEC450.21(B) 5/13/2002 8:56:44 AM
|
Electrical Rough-In | 5/10/2002 | 5/10/2002 | 5/10/2002 | P | PART |
Mike Kinnear
|
|
|
RENE ###-#### ok cover walls stair 100J, 106P,101C, 101E, 104C, 101F, part corr. 100D, part 110A, part 101P. 5/10/2002 3:22:14 PM
|
Electrical Rough-In | 5/2/2002 | 5/3/2002 | 5/3/2002 | A | PART |
Mike Kinnear
|
|
|
conference Dion ###-#### conf regarding transformer bonding & grounding 5/3/2002 8:30:50 AM
|
Electrical Rough-In | 4/23/2002 | 4/24/2002 | 4/24/2002 | A | PART |
Mike Kinnear
|
|
|
deeon- ###-#### r/i ok cover walls only 3rd floor preim. walls, level 1 clean rm. ext walls,100D & 100E corridors, 3rd floor int. waffles slab walls , toilets 100U & V, jant rm 101M 4/24/2002 10:24:45 AM
|
Electrical Rough-In | 4/11/2002 | 4/11/2002 | 4/11/2002 | P | PART |
Mike Kinnear
|
|
|
wall cover ###-#### deeon ok cover walls only lobby100B part, corr. 100C part, 104D part,102A, 105b PART, 112A, 112B, 112C, 100B, 101J part, storage 110A part, HPM aisle 002B, 001G, 001H, 001H, 000A stair6, 001F, 001E, 001D, 001C, 001B, 002A, & stair5 000F part. 4/11/2002 2:05:57 PM
|
Electrical Rough-In | 4/2/2002 | 4/3/2002 | 4/3/2002 | A | PART |
Mike Kinnear
|
|
|
deeon- cell ###-#### ok cover ones wall sub fab aisle 003A, HPM aisle vestibule 002C one side, & main switch gear rm 101K walls only 4/3/2002 9:28:11 AM
|
Electrical Rough-In | 3/19/2002 | 3/20/2002 | 3/20/2002 | A | PART |
Mike Kinnear
|
|
|
underground insp deeon- cell ###-#### ok cover underground for pimmary power 3/20/2002 8:02:02 AM
|