Final | 4/24/2003 | 4/25/2003 | 4/25/2003 | P | PASS |
Pat Lass
|
|
|
after 1:30 ###-####
|
Final | 2/18/2003 | 2/19/2003 | 2/19/2003 | A | FAIL |
Tim McCullough
|
|
|
Scheduled by a contractor via Hello! on 2/18/2003 at 2:36:05 PM. Contact: ###-####.
correction ,rev. polarity&1 line/&load rev. in old garage.called contractor. 2/19/2003 11:07:18 AM
|
Electrical Rough-In | 6/13/2002 | 6/13/2002 | 6/13/2002 | P | PASS |
Pat Lass
|
|
|
rob ###-####
Phase 2 ok 6/13/2002 3:15:10 PM
|
Rough-In Permanent Service | 5/29/2002 | 5/29/2002 | 5/29/2002 | P | PASS |
Pat Lass
|
|
|
###-#### HEATHER
|
Permanent Service | 5/16/2002 | 5/16/2002 | 5/16/2002 | P | PASS |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 05/16/2002 at 08:10:00. Contact: ###-####.
P/S U/G R Ok 5/16/2002 2:23:34 PM
|