Electrical Rough-In | 10/10/2002 | 10/11/2002 | 10/11/2002 | A | PASS |
Jack Frank
|
|
|
Phone #: ###-#### Internet Inspection Request from: Amy Lawson r/i ok 10/11/2002 2:22:07 PM
|
Electrical Rough-In | 8/19/2002 | 8/20/2002 | 8/20/2002 | A | PART |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 08/19/2002 at 15:44:53. Contact: ###-####. under ground to garage and in garage ok 8/20/2002 10:06:31 AM
|
Electrical Rough-In | 8/15/2002 | 8/16/2002 | 8/16/2002 | P | FAIL |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 08/15/2002 at 16:20:02. Contact: ###-####. cor. posted met with owner250.8,110.3 (B) breakers, 300.5, 250.52(C), 352.46and 300.4(F), 110.14(B) insulation for splices jbox, 110.26 cleraence in front of panels in garage 8/16/2002 6:53:00 PM
|
Electrical Rough-In | 7/29/2002 | 7/30/2002 | 7/30/2002 | A | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 07/29/2002 at 13:21:12. Contact: ###-####. conference ok only 7/30/2002 12:34:30 PM
|