Final | 11/19/2002 | 11/19/2002 | 11/19/2002 | P | PASS |
Jack Frank
|
|
|
###-#### brad survey posted still needs box extension for combo switch outlet by cash wrap this is the thrid time I have told contractor
final ok 11/19/2002 5:08:08 PM
|
Final | 11/15/2002 | 11/18/2002 | 11/18/2002 | A | FAIL |
Jack Frank
|
|
|
###-#### corrections not made called 11/18/2002 12:03:24 PM
|
Final | 11/15/2002 | 11/15/2002 | 11/15/2002 | A | FAIL |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 11/15/2002 at 07:27:46. Contact: ###-####. cor. posted met with contractor 314.20 250.146(A) boxes with raised covers, 300.11 use own support wires too support raceways in grid ceiling, 300.7 seal conduits entering cooler,, 250.6 arrange wires in conduits to contacter to prevent objectionable currents, 110.12(A) seal unused KOs cor. posted to BLD02-02261 support low voltage cables laying on grid ceiling $42.00 reinspection fee due 11/15/2002 11:42:55 AM
|
Electrical Rough-In | 10/28/2002 | 10/28/2002 | 10/28/2002 | P | PASS |
Mike Kinnear
|
|
|
brad--r/i on ceiling; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok cover ceiling only 10/28/2002 2:54:46 PM
|
Electrical Rough-In | 10/15/2002 | 10/15/2002 | 10/15/2002 | P | PART |
Jack Frank
|
|
|
Phone #: ###-#### Internet Inspection Request from: Amy Lawson walls ok 10/15/2002 3:06:23 PM
|
Electrical Rough-In | 10/14/2002 | 10/14/2002 | 10/14/2002 | P | PART |
Jack Frank
|
|
|
###-#### u/g ok only cor. posted for walls 300.4(D), 330.30(C) called 10/14/2002 3:49:19 PM
|