Final | 7/21/2003 | 7/22/2003 | 7/22/2003 | A | PASS |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 7/21/2003 at 1:21:03 PM. Contact: ###-####. ok 7/22/2003 9:25:34 AM
|
Final | 7/21/2003 | 7/21/2003 | 7/21/2003 | P | FAIL |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 7/21/2003 at 8:22:24 AM. Contact: ###-####. no final or temp too many people there , they are open and serving food 7/21/2003 1:41:51 PM
|
Electrical Rough-In | 7/17/2003 | 7/17/2003 | 7/17/2003 | P | PASS |
Jim Schmer
|
|
|
Scheduled by a contractor via Hello! on 7/17/2003 at 10:42:35 AM. Contact: ###-####. underground for lts in back of building 7/17/2003 12:26:26 PM
|
Final | 7/11/2003 | 7/11/2003 | 7/11/2003 | P | NR |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 7/11/2003 at 8:14:31 AM. Contact: ###-####. called needs gfci for kit recepts 7/14/2003 10:40:47 AM
|
Electrical Rough-In | 7/3/2003 | 7/3/2003 | 7/3/2003 | P | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 7/3/2003 at 10:05:15 AM. Contact: ###-####. ceiling ok for 2 restrms and hallway 7/3/2003 1:12:24 PM
|
Electrical Rough-In | 7/1/2003 | 7/1/2003 | 7/1/2003 | P | PASS |
Jim Schmer
|
|
|
###-#### ceiling inspection
|
Permanent Service | 6/25/2003 | 6/26/2003 | 6/26/2003 | P | PASS |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 6/25/2003 at 3:32:44 PM. Contact: ###-####. p/s u/g rec. ok 6/26/2003 3:54:04 PM
|
Conference | 6/16/2003 | 6/18/2003 | 6/18/2003 | A | PASS |
Mike Kinnear
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Barbara Moore//Inspection moved from the 06/17/03 to 06/18/03 per Jim Schmer ok conf regarding fire pump 6/18/2003 12:48:31 PM
|
Electrical Rough-In | 5/27/2003 | 5/27/2003 | 5/27/2003 | A | PASS |
Jack Frank
|
|
|
r/i for walls ok
|
Electrical Rough-In | 5/21/2003 | 5/21/2003 | 5/21/2003 | P | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 5/21/2003 at 9:33:44 AM. Contact: ###-####. see blue highlighed walls on print needs bushings for rigid nipples both dimmer bank locations 5/21/2003 2:52:58 PM
|
Electrical Rough-In | 4/28/2003 | 4/28/2003 | 4/28/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 4/28/2003 at 9:32:55 AM. Contact: ###-####. ok cover under slab conduit 4/28/2003 4:53:56 PM
|
Conference | 4/24/2003 | 4/24/2003 | 4/24/2003 | P | DONE |
Tim McCullough
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Annette Moore
switch gear tapp must have tested 4/24/2003 2:55:38 PM
|