Final | 7/25/2003 | 7/25/2003 | 7/25/2003 | A | CANC |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 7/25/2003 at 7:00:46 AM. Contact: ###-####. resched pm 7/25/2003 10:49:34 AM
|
Final | 7/25/2003 | 7/25/2003 | 7/25/2003 | P | PASS |
Mike Kinnear
|
|
|
ok final 7/25/2003 1:08:54 PM
|
Electrical Rough-In | 6/13/2003 | 6/13/2003 | 6/13/2003 | A | PASS |
Tim McCullough
|
|
|
Scheduled by a contractor via Hello! on 6/13/2003 at 12:02:52 AM. Contact: ###-####.
ri/ok 6/13/2003 11:39:28 AM
|
Electrical Rough-In | 5/13/2003 | 5/14/2003 | 5/14/2003 | A | PASS |
Tim McCullough
|
|
|
###-#### shawn