Electrical Rough-In | 2/27/2004 | 2/27/2004 | 2/27/2004 | P | CANC |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 2/27/2004 at 8:14:03 AM. Contact: ###-####. wrong type inspection 2/27/2004 4:23:43 PM
|
Final | 2/27/2004 | 2/27/2004 | 2/27/2004 | P | PASS |
Mike Kinnear
|
|
|
ok final core & shell
|
Electrical Rough-In | 1/8/2004 | 1/9/2004 | 1/9/2004 | A | FAIL |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 1/8/2004 at 10:19:05 AM. Contact: ###-####. this is for T.I. inspection wrong permit number they do not have T.I. elect. permit yet 1/9/2004 9:57:02 AM
|
Permanent Service | 1/6/2004 | 1/6/2004 | 1/6/2004 | P | PASS |
Mike Kinnear
|
|
|
p/s u/g n ok
|
Rough-In Permanent Service | 1/6/2004 | 1/6/2004 | 1/6/2004 | P | CANC |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 1/6/2004 at 8:33:30 AM. Contact: ###-####. wrong type inspection 1/6/2004 12:48:20 PM
|
Electrical Rough-In | 12/31/2003 | 1/5/2004 | 1/5/2004 | P | NR |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 12/31/2003 at 9:02:48 AM. Contact: ###-####. conf regarding service 1/5/2004 4:00:28 PM
|
Electrical Rough-In | 12/29/2003 | 12/30/2003 | 12/30/2003 | A | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 12/29/2003 at 3:25:35 PM. Contact: ###-####. ok cover under slab conduit by pool area 12/30/2003 8:38:53 AM
|
Electrical Rough-In | 12/16/2003 | 12/16/2003 | 12/16/2003 | P | NR |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 12/16/2003 at 8:22:41 AM. Contact: ###-####. this under wrong permit # they going to conduit in the wall not underground 12/16/2003 3:29:38 PM
|
Final | 12/15/2003 | 12/16/2003 | 12/16/2003 | A | NR |
Mike Kinnear
|
|
|
wayne-- ###-#### contractor not ready 12/16/2003 9:18:13 AM
|
Electrical Rough-In | 12/12/2003 | 12/15/2003 | 12/15/2003 | P | CANC |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 12/12/2003 at 9:47:41 AM. Contact: ###-####. wrong ele permit # they to get ele that goes with bld# 12/15/2003 6:04:11 PM
|
Electrical Rough-In | 12/3/2003 | 12/4/2003 | 12/4/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 12/3/2003 at 1:07:59 PM. Contact: ###-####. ok cover walls & hard lid ceilings per shown on print 12/4/2003 4:20:29 PM
|
Electrical Rough-In | 11/26/2003 | 11/26/2003 | 11/26/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 11/26/2003 at 8:30:22 AM. Contact: ###-####. ok cover part bathrooms 2nd floor walls & ceiling hard lid 11/26/2003 1:56:17 PM
|
Electrical Rough-In | 11/17/2003 | 11/18/2003 | 11/18/2003 | A | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 11/17/2003 at 1:05:14 PM. Contact: ###-####. ok cover in the slab conduit the only thing left is the pool 11/18/2003 9:12:54 AM
|
Electrical Rough-In | 11/5/2003 | 11/5/2003 | 11/5/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 11/5/2003 at 8:34:42 AM. Contact: ###-####. ok cover slab conduit & walls shown on print 11/5/2003 3:47:13 PM
|
Electrical Rough-In | 11/3/2003 | 11/3/2003 | 11/3/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 11/3/2003 at 10:37:41 AM. Contact: ###-####. ok cover duct bank 11/3/2003 1:32:12 PM
|
Electrical Rough-In | 10/31/2003 | 10/31/2003 | 10/31/2003 | P | FAIL |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 10/31/2003 at 10:19:01 AM. Contact: ###-####. no one at job site called left message 10/31/2003 4:41:34 PM
|
Electrical Rough-In | 10/30/2003 | 10/30/2003 | 10/30/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 10/30/2003 at 9:21:00 AM. Contact: ###-####. ok cover underground parking lot conduit. duct bank not approved needs seperation between conduits 10/30/2003 4:05:00 PM
|
Electrical Rough-In | 10/28/2003 | 10/28/2003 | 10/28/2003 | P | PART |
Pat Lass
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
U/G Ok 10/28/2003 1:01:08 PM
|
Electrical Rough-In | 10/27/2003 | 10/27/2003 | 10/27/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 10/27/2003 at 10:57:41 AM. Contact: ###-####. ok cover under ground site lighting conduit on print 10/27/2003 1:49:31 PM
|
Electrical Rough-In | 10/23/2003 | 10/23/2003 | 10/23/2003 | P | PASS |
Mike Kinnear
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Darla Downs ok cover soffit marked on print 10/23/2003 3:49:12 PM
|
Electrical Rough-In | 10/1/2003 | 10/2/2003 | 10/2/2003 | A | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 10/1/2003 at 9:05:58 AM. Contact: ###-####. ok cover part underground conduit 1st floor shown on print 10/2/2003 9:39:22 AM
|
Electrical Rough-In | 9/22/2003 | 9/22/2003 | 9/22/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 9/22/2003 at 11:28:32 AM. Contact: ###-####. ok cover slab concrete 2nd floor 9/22/2003 4:28:22 PM
|
Electrical Rough-In | 9/16/2003 | 9/16/2003 | 9/16/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 9/16/2003 at 9:39:00 AM. Contact: ###-####. ok cover part in slab 1st floor marked on print 9/16/2003 2:07:56 PM
|
Electrical Rough-In | 9/12/2003 | 9/12/2003 | 9/12/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 9/12/2003 at 10:35:39 AM. Contact: ###-####. ok cover part 2nd floor pan deck concrete 9/12/2003 4:58:38 PM
|
Electrical Rough-In | 8/27/2003 | 8/27/2003 | 8/27/2003 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 8/27/2003 at 8:21:04 AM. Contact: ###-####. ok cover part area floor boxes id on print 8/27/2003 3:24:51 PM
|
Electrical Rough-In | 8/5/2003 | 8/6/2003 | 8/6/2003 | A | PART |
Mike Kinnear
|
|
|
###-#### jim ok cover underground conduit service & sub feeds 8/6/2003 10:46:25 AM
|
Electrical Rough-In | 7/22/2003 | 7/22/2003 | 7/22/2003 | P | PASS |
Jim Schmer
|
|
|
ufer ground
|