Final | 5/27/2004 | 5/27/2004 | 5/27/2004 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 5/27/2004 at 9:13:32 AM. Contact: ###-####.
|
Final | 5/14/2004 | 5/17/2004 | 5/17/2004 | A | PART |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 5/14/2004 at 11:35:35 AM. Contact: ###-####. first floor units and hallway 5/17/2004 10:09:41 AM
|
Final | 5/14/2004 | 5/14/2004 | 5/14/2004 | P | CANC |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 5/14/2004 at 10:52:44 AM. Contact: ###-####.
|
Final | 5/7/2004 | 5/10/2004 | 5/10/2004 | A | PART |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 5/7/2004 at 8:48:48 AM. Contact: ###-####. final on second floor ok 5/10/2004 10:19:09 AM
|
Final | 5/7/2004 | 5/7/2004 | 5/7/2004 | A | PART |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 5/7/2004 at 6:54:29 AM. Contact: ###-####. final for third floor ok 5/7/2004 10:18:54 AM
|
Electrical Rough-In | 5/5/2004 | 5/6/2004 | 5/6/2004 | A | PASS |
Joe Ray
|
|
|
###-#### rick first floor ceiling ok 5/6/2004 9:50:22 AM
|
Electrical Rough-In | 4/5/2004 | 4/5/2004 | 4/5/2004 | P | PART |
Jack Frank
|
|
|
rick ###-#### ceilings 2nd and 3rd floor corridors 4/5/2004 12:28:11 PM
|
Electrical Rough-In | 3/3/2004 | 3/4/2004 | 3/4/2004 | A | PART |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 3/3/2004 at 3:24:23 PM. Contact: ###-####. r/i firsy floor ok 3/4/2004 10:49:18 AM
|
Electrical Rough-In | 2/24/2004 | 2/25/2004 | 2/25/2004 | A | PART |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 2/24/2004 at 4:41:13 PM. Contact: ###-####. ceilings in units ok for cover /rooms in mc cable ok / units not ready 2/25/2004 9:45:47 AM
|
Electrical Rough-In | 2/12/2004 | 2/13/2004 | 2/13/2004 | A | PART |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 2/12/2004 at 1:30:19 PM. Contact: ###-####. part. r/i 1 st floor 2/13/2004 10:08:53 AM
|
Electrical Rough-In | 2/12/2004 | 2/12/2004 | 2/12/2004 | P | FAIL |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 2/12/2004 at 11:22:34 AM. walls covered before inspection 2/12/2004 12:55:27 PM
|
Electrical Rough-In | 2/9/2004 | 2/9/2004 | 2/9/2004 | P | PASS |
Joe Ray
|
|
|
rick rough in 2nd floor only; Phone #: ###-#### Internet Inspection Request from: Annette Moore r/i second floor ok except hallway ceilings 2/9/2004 1:30:08 PM
|
Electrical Rough-In | 1/14/2004 | 1/14/2004 | 1/14/2004 | P | PASS |
Joe Ray
|
|
|
RICK INSPECTION IS ON THE 3RD FLOOR; Phone #: ###-#### Internet Inspection Request from: Darla Downs r/i units and walls in hallway ok for cover 1/14/2004 2:26:39 PM
|
Electrical Rough-In | 1/8/2004 | 1/9/2004 | 1/9/2004 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 1/8/2004 at 2:15:15 PM. Contact: ###-####. ok cover hard lid ceiling 3rd floor only 1/9/2004 1:18:47 PM
|
Electrical Rough-In | 12/12/2003 | 12/15/2003 | 12/15/2003 | A | PART |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 12/12/2003 at 4:32:02 PM. Contact: ###-####. conference with contr 12/15/2003 11:04:12 AM
|
Permanent Service | 11/21/2003 | 11/21/2003 | 11/21/2003 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 11/21/2003 at 10:08:34 AM. Contact: ###-####. p/s ug n ok 11/21/2003 12:59:32 PM
|
Electrical Rough-In | 10/13/2003 | 10/14/2003 | 10/14/2003 | P | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 10/13/2003 at 4:05:09 PM. Contact: ###-####. parking lot light bases ok to pour with concrete 10/14/2003 2:10:11 PM
|
Electrical Rough-In | 9/16/2003 | 9/17/2003 | 9/17/2003 | A | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 9/16/2003 at 12:44:18 PM. Contact: ###-####. underground ok for cover 9/17/2003 9:54:25 AM
|