Final | 10/13/2004 | 10/15/2004 | 10/15/2004 | A | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 10/13/2004 at 1:28:11 PM. Contact: ###-####.
|
Conference | 9/17/2004 | 9/20/2004 | 9/20/2004 | A | DONE |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 9/17/2004 at 1:21:37 PM. Contact: ###-####. clearances above panels/reengineer per jim schmer 9/20/2004 9:41:22 AM
|
Electrical Rough-In | 9/17/2004 | 9/20/2004 | 9/20/2004 | A | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 9/17/2004 at 1:20:37 PM. Contact: ###-####. r/i walls completed ok for cover 9/20/2004 9:30:49 AM
|
Electrical Rough-In | 9/14/2004 | 9/15/2004 | 9/15/2004 | A | PASS |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 9/14/2004 at 4:06:42 PM. Contact: ###-####. middle section ok 9/15/2004 10:01:13 AM
|
Electrical Rough-In | 9/2/2004 | 9/3/2004 | 9/3/2004 | A | PART |
Joe Ray
|
|
|
Scheduled by a contractor via Hello! on 9/2/2004 at 9:10:41 AM. Contact: ###-####. particial hard ceiling and walls ok 9/3/2004 9:32:20 AM
|