Final | 5/24/2006 | 5/24/2006 | 5/24/2006 | A | NR |
Jack Frank
|
|
|
called contractor he will check status of job
|
Rough-In Permanent Service | 9/3/2004 | 9/7/2004 | 9/7/2004 | A | PASS |
Jack Frank
|
|
|
We:1)Replaced the existing service with a new 200 amp service and all-in-one meter/panel. 2)Extended the existing two 120 volt circuits and the one 220 volt circuit from under the house out to the new all-in-one panel. 3)Installed 2 new ground rods,(plastic water main). 4) Seperated the grounds and neutrals at the existing indoor panel.Thanks!!!Dan.; Phone #: ###-#### Internet Inspection Request from: Dan Mitchell
remove grd from sub panel take it to p/s, terminate all equip grd in sub panel, dryer and range 4 wire recepts and pigtails
p/s o/h rec. ok 9/7/2004 8:28:08 AM
|