Final | 3/9/2005 | 3/11/2005 | 3/11/2005 | P | PASS |
William E Thomas
|
|
|
Phone #: ###-#### Internet Inspection Request from: Joe Thomas
|
Electrical Rough-In | 2/17/2005 | 2/17/2005 | 2/17/2005 | A | FAIL |
Jack Frank
|
|
|
ceiling cover for grid in phase 2; Phone #: ###-#### Internet Inspection Request from: Joe Thomas cor. posted called 300.11(ABC) same corrections posted 12-09-04 2/17/2005 11:00:56 AM
|
Electrical Rough-In | 2/17/2005 | 2/17/2005 | 2/17/2005 | P | PASS |
Jack Frank
|
|
|
cover of ceiling grid in phase 2; Phone #: ###-#### Internet Inspection Request from: Joe Thomas 2/17/2005 1:30:07 PM
|
Electrical Rough-In | 2/16/2005 | 2/16/2005 | 2/16/2005 | P | FAIL |
Mike Kinnear
|
|
|
Cover for ceiling tile; Phone #: ###-#### Internet Inspection Request from: Joe Thomas corrections not made called joe he meet me & he to fix corrections 2/16/2005 4:01:23 PM
|
Electrical Rough-In | 2/15/2005 | 2/15/2005 | 2/15/2005 | P | FAIL |
Bob Reichert
|
|
|
Ceiling inspection for phase 2 cover of ceiling.; Phone #: ###-#### Internet Inspection Request from: Joe Thomas 358.30(A) emt shall be supported within 3' of box, 314.17(A) openings shall be closed (heater), 300.11(A) independent ceiling wires shall be identified, 300.11(2)(B) raceways shall not be used as support for non-electric equipment. Note: support wires for fixtures require min 2 wires for seismic 2/15/2005 2:12:31 PM
|
Electrical Rough-In | 1/24/2005 | 1/24/2005 | 1/24/2005 | P | PASS |
Bob Reichert
|
|
|
rough in for walls in phase 2; Phone #: ###-#### Internet Inspection Request from: Joe Thomas ok to cover steel walls 1/24/2005 1:16:11 PM
|
Electrical Rough-In | 12/29/2004 | 12/29/2004 | 12/29/2004 | P | PART |
Bob Reichert
|
|
|
ceiling inspection for cover where ceiling grid is installed in phase 1; Phone #: ###-#### Internet Inspection Request from: Joe Thomas ok to cover ceiling only for phase 1 where grid is up. Corrections made. 12/29/2004 1:52:47 PM
|
Electrical Rough-In | 12/9/2004 | 12/9/2004 | 12/9/2004 | P | FAIL |
Jack Frank
|
|
|
approval for ceiling cover in areas with grid ceiling; Phone #: ###-#### Internet Inspection Request from: Joe Thomas cor. posted called, 300.11(ABC) raceways or cables shall not support cables or raceways, if wires are used do as code noted states 314.23(D) shall support boxes, 110.26(F)(1) provide clearence for all panels (panels above ceiling grid, all wiring shall meet 517 for patient care area 800.2,760.2,725.2 remove abandoned cables, 800.5&6, 760.5&6, 725.5&6 support, protect, and install as code noted states B C C no violations retained 12/9/2004 2:16:12 PM
|
Electrical Rough-In | 12/8/2004 | 12/8/2004 | 12/8/2004 | P | NR |
Bob Reichert
|
|
|
Approval for cover on grid ceiling; Phone #: ###-#### Internet Inspection Request from: Joe Thomas talked to contr. and told him he needs ko seals in boxes,strapping for mc cable over panel, and conduit, also to determine what abandoned cabling in ceiling needs to be removed. He says that job will be done in phases which is why one fixture is covered by temp wall. 12/8/2004 2:00:16 PM
|
Electrical Rough-In | 11/10/2004 | 11/10/2004 | 11/10/2004 | A | PART |
Jack Frank
|
|
|
Rough in for walls of dentists office; Phone #: ###-#### Internet Inspection Request from: Joe Thomas ok 11/10/2004 9:40:28 AM
|
Electrical Rough-In | 11/8/2004 | 11/9/2004 | 11/9/2004 | A | FAIL |
Pat Lass
|
|
|
###-#### Rough in for walls of dentists office. Project is being done in 2 phases. This is for the 1st phase.; Phone #: ###-#### Internet Inspection Request from: Joe Thomas 11/9/2004 8:07:01 AM
300.4 Protection Against Physical Damage.
Where subject to physical damage, conductors shall be adequately protected.
(D) Cables and Raceways Parallel to Framing Members.
11/9/2004 9:52:55 AM
|