Final | 2/9/2007 | 2/9/2007 | 2/9/2007 | A | PASS |
Bob Reichert
|
|
|
ok to final per conversation w/ 425
|
Final | 1/29/2007 | 1/29/2007 | 1/29/2007 | P | PART |
Bob Reichert
|
|
|
signed struct card for hotel shell and foundations, will final ltr
|
Final | 1/23/2007 | 1/24/2007 | 1/24/2007 | A | PART |
Bob Reichert
|
|
|
CONTACT: GREG PACK - RE-INSPECTION, PARTIAL FINAL Phone #: ###-#### left corr notice,BCC-4-05-33(A)(B) all equipment shall be listed by a nationally recognized testing lab, NEC 110.3(A)(1) listed or labelled equipment shall be suitable for installation and use, told 2 weeks to fix or further action will be taken, signed plans, checking on permits, then can do sign-off
|
Final | 1/22/2007 | 1/23/2007 | 1/23/2007 | A | PART |
Bob Reichert
|
|
|
Contact: Greg Pack - partial final-1st floor Phone #: ###-#### looked at new mech room for fire prot, told contr to find out about jockey pump listing, drip protection over panels, labels, need elev request for inspections
|
ELE-Aging Inspection | 1/22/2007 | 1/22/2007 | 1/22/2007 | | DONE |
Bob Reichert
|
|
|
suc
|
ELE-Aging Inspection | 11/20/2006 | 11/20/2006 | 11/20/2006 | | DONE |
Bob Reichert
|
|
|
suc
|
ELE-Aging Inspection | 9/11/2006 | 9/11/2006 | 9/11/2006 | | DONE |
Bob Reichert
|
|
|
suc
|
ELE-Aging Inspection | 7/10/2006 | 7/10/2006 | 7/10/2006 | | DONE |
Bob Reichert
|
|
|
suc
|
ELE-Aging Inspection | 5/9/2006 | 5/9/2006 | 5/9/2006 | | DONE |
Bob Reichert
|
|
|
project suc
|
Electrical Rough-In | 3/8/2006 | 3/8/2006 | 3/8/2006 | P | PART |
Bob Reichert
|
|
|
CONTACT: LYLE DEAN - TEMPORARY OCCUPANCY INSPECTION PLEASE.; Phone #: ###-#### Internet Inspection Request from: Deb McCoy signed t/o card for first 3 floors of parking garage only
|
Electrical Rough-In | 3/1/2006 | 3/2/2006 | 3/2/2006 | A | CANC |
Bob Reichert
|
|
|
CONTACT: LYLE DEAN - TEMPORARY OCCUPANCY INSPECTION; Phone #: ###-#### Internet Inspection Request from: Deb McCoy see final
|
Final | 3/2/2006 | 3/2/2006 | 3/2/2006 | A | PART |
Bob Reichert
|
|
|
CONTACT: LYLE DEAN - TEMPORARY OCCUPANCY INSPECTION; Phone #: ###-#### Internet Inspection Request from: Deb McCoy corrections made for first 3 floors of parking garage. Went to sign t/o card, but no card available.
|
Conference | 3/1/2006 | 3/1/2006 | 3/1/2006 | P | DONE |
Bob Reichert
|
|
|
Contact: Shane Korte - Parking equipment portion; Phone #: ###-#### Internet Inspection Request from: Deb McCoy talked about options to segregate class 2&3 wiring from class 1 at parking lot attendant booth
|
Electrical Rough-In | 2/28/2006 | 3/1/2006 | 3/1/2006 | A | PART |
Bob Reichert
|
|
|
CONTACT: LYLE DEAN - TEMPORARY FINAL FOR FLOORS 1,2 & 3 ; Phone #: ###-#### Internet Inspection Request from: Deb McCoy most corrections done, will fix some attendant items and call back to get t/o
|
Final | 2/24/2006 | 2/24/2006 | 2/24/2006 | P | FAIL |
Bob Reichert
|
|
|
CONTACT: GREG PACK; Phone #: ###-#### Internet Inspection Request from: Deb McCoy met contr, left corr notice, 408.4 circuit directory shall be clear, concise evident for each circuit, 358.12(5) emt shall not be used for fixture support, 358.26 there shall not be over 360 degrees bend in emt between pull points,358.30(A) emt shall be securely fastened within 3' of conduit body, 110.12(A) unused openings shall be closed in boxes, 314.25 boxes shall have covers installed, 410.14(B) electric discharge fixtures surface mounted over concealed boxes, unless designed to be supported by box, shall be provided with openings to provide wiring access, 300.3(C)(1) all circuit conductors shall have insulation rating equal to maximum circuit voltage applied to any conductor in enclosure, 400.8(2) flexible cord shall not be run thru walls, 110.2 equipment shall be acceptable only if approved (parking attendant stations), 427.11 pipeline heating equipment shall be installed to avoid physical damage, NOTE: access to 4th floor via stairs shall be prohibited
|
Final | 2/24/2006 | 2/24/2006 | 2/24/2006 | P | FAIL |
Pat Lass
|
|
|
see bobs notes
|
Permanent Service | 1/10/2006 | 1/11/2006 | 1/11/2006 | A | CANC |
Bob Reichert
|
|
|
contact: Lyle Dean; Phone #: ###-#### Internet Inspection Request from: Deb McCoy wrong permit , they will fix and recall
|
Electrical Rough-In | 12/28/2005 | 12/28/2005 | 12/28/2005 | P | PART |
Bob Reichert
|
|
|
Inspection for 1st floor lobby. Contact Lyle Dean ; Phone #: ###-#### Internet Inspection Request from: Shelli Daylong ok to cover walls, elect room anop
|
Electrical Rough-In | 12/27/2005 | 12/27/2005 | 12/27/2005 | P | PART |
Bob Reichert
|
|
|
lyle dean; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok to cover hall anop, they need to revisit panel locations due to overhead piping interferences
|
Electrical Rough-In | 11/4/2005 | 11/7/2005 | 11/7/2005 | A | PASS |
Bob Reichert
|
|
|
CONTACT: LYLE DEAN 1ST FLOOR INSPECTION; Phone #: ###-#### Internet Inspection Request from: Deb McCoy ok to cover poured in u/g by elect room
|
Electrical Rough-In | 11/3/2005 | 11/4/2005 | 11/4/2005 | A | PASS |
Bob Reichert
|
|
|
Contact: Lyle Dean - 1st floor inspection; Phone #: ###-#### Internet Inspection Request from: Deb McCoy u/g ok to cover from elect room to sidewalk in 1st floor garage
|
Electrical Rough-In | 11/2/2005 | 11/3/2005 | 11/3/2005 | A | PART |
Bob Reichert
|
|
|
Please call Lyle Dean if you have any questions.; Phone #: ###-#### Internet Inspection Request from: Shelli Daylong looking at u/g by elect room, nw stairwell for f/a power and lites.
|
Electrical Rough-In | 10/12/2005 | 10/12/2005 | 10/12/2005 | P | PART |
Bob Reichert
|
|
|
CONTACT: LYLE DEAN 2ND FLOOR INSPECTION; Phone #: ###-#### Internet Inspection Request from: Deb McCoy 2nd floor ramp ok to cover anop
|
Electrical Rough-In | 10/6/2005 | 10/7/2005 | 10/7/2005 | A | PART |
Bob Reichert
|
|
|
CONTACT: LYLE DEAN - 3RD FLOOR PARKING GARAGE RAMP INSPECTION; Phone #: ###-#### Internet Inspection Request from: Deb McCoy ramp 3rd fl ok to pour anop
|
Electrical Rough-In | 10/5/2005 | 10/6/2005 | 10/6/2005 | A | PASS |
Bob Reichert
|
|
|
CONTACT: LYLE DEAN - INSPECTION IS FOR THE 3RD FLOOR.; Phone #: ###-#### Internet Inspection Request from: Deb McCoy ok to cover 3rd floor parking deck anop
|
Electrical Rough-In | 9/30/2005 | 9/30/2005 | 9/30/2005 | P | PART |
Bob Reichert
|
|
|
CONTACT: LYLE DEAN - INSPECTION ID FOR THE 4TH FLOOR; Phone #: ###-#### Internet Inspection Request from: Deb McCoy ok to cover 4th floor garage deck (mark plans next trip, Lyle not here to find plans)
|
Electrical Rough-In | 9/28/2005 | 9/29/2005 | 9/29/2005 | A | PART |
Pat Lass
|
|
|
CONTACT: LYLE DEAN - INSPECTION ON 2ND FLOOR; Phone #: ###-#### Internet Inspection Request from: Deb McCoy 2nd floor deck r/i complete
|
Electrical Rough-In | 9/26/2005 | 9/27/2005 | 9/27/2005 | A | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 9/26/2005 at 3:06:36 PM. Contact: ###-####. anop
|
Electrical Rough-In | 9/21/2005 | 9/21/2005 | 9/21/2005 | P | PASS |
William E Thomas
|
|
|
Contact: Lyle Dean - 1st floor re -inspection; Phone #: ###-#### Internet Inspection Request from: Deb McCoy as noted on prints for slab ok to cover
|
Electrical Rough-In | 9/20/2005 | 9/21/2005 | 9/21/2005 | A | NR |
Bob Reichert
|
|
|
Contact: Lyle Dean- Slab rough-in inside building, 1st floor. corner of Myrtle & capitol; Phone #: ###-#### Internet Inspection Request from: Deb McCoy will re-call
|
Permanent Service | 9/13/2005 | 9/13/2005 | 9/13/2005 | P | PASS |
Pat Lass
|
|
|
CONTACT: LEON SHEFFIELD; Phone #: ###-#### Internet Inspection Request from: Deb McCoy
|
Permanent Service | 9/8/2005 | 9/9/2005 | 9/9/2005 | A | PART |
Pat Lass
|
|
|
CONTACT: LEON SHEFFIELD; Phone #: ###-#### Internet Inspection Request from: Deb McCoy P/S U/G N Ok for power contractor will insure weatherproof shed to be in place prior to connection.
|
Conference | 9/7/2005 | 9/8/2005 | 9/8/2005 | A | PART |
Pat Lass
|
|
|
CONTACT: LEON SHEFFIELD; Phone #: ###-#### Internet Inspection Request from: Deb McCoy talked ab out inclosure for service
|
Electrical Rough-In | 9/1/2005 | 9/2/2005 | 9/2/2005 | A | PART |
Pat Lass
|
|
|
CONTACT: LYLE DEAN INSPECTION FOR 2ND & 4TH FLOORS; Phone #: ###-#### Internet Inspection Request from: Deb McCoy
|
Electrical Rough-In | 8/25/2005 | 8/26/2005 | 8/26/2005 | A | PART |
Pat Lass
|
|
|
###-#### Contact: Lyle Dean - rough-in for 3rd and 4th floor s.w. stairs area; Phone #: ###-#### Internet Inspection Request from: Deb McCoy anop
|
Electrical Rough-In | 8/15/2005 | 8/16/2005 | 8/16/2005 | A | PART |
Pat Lass
|
|
|
CONTACT: LYLE DEAN - ROUGH-IN ON 2ND FLOOR; Phone #: ###-#### Internet Inspection Request from: Deb McCoy anop
|
Electrical Rough-In | 8/3/2005 | 8/3/2005 | 8/3/2005 | P | PART |
Pat Lass
|
|
|
CONTACT: LYLE DEAN; Phone #: ###-#### Internet Inspection Request from: Deb McCoy anop
|
Electrical Rough-In | 7/15/2005 | 7/15/2005 | 7/15/2005 | P | PART |
Pat Lass
|
|
|
Contact Doug Loomis; Phone #: ###-#### Internet Inspection Request from: Shelli Daylong sight lighting allong Broad st ok
|
Electrical Rough-In | 6/14/2005 | 6/14/2005 | 6/14/2005 | P | PART |
Pat Lass
|
|
|
Please call Lyle Dean with any questions.; Phone #: ###-#### Internet Inspection Request from: Shelli Daylong 4th floor deck anop
|
Electrical Rough-In | 5/25/2005 | 5/26/2005 | 5/26/2005 | A | PART |
Pat Lass
|
|
|
CONTACT: LYLE DEAN - 2ND FLOOR INSPECTION; Phone #: ###-#### Internet Inspection Request from: Deb McCoy ANOP
|
Electrical Rough-In | 3/29/2005 | 3/30/2005 | 3/30/2005 | A | PART |
Pat Lass
|
|
|
CONTACT LYLE DEAN. UNDERGROUND INSPECTION.; Phone #: ###-#### Internet Inspection Request from: Shelli Daylong
Partial U/G 3/30/2005 8:34:43 AM
|
Electrical Rough-In | 3/23/2005 | 3/24/2005 | 3/24/2005 | A | PART |
Pat Lass
|
|
|
Contact: Lyle Dean - Underground insp. - Please inspect as early as possible; Phone #: ###-#### Internet Inspection Request from: Deb McCoy
6 in duct bank to outside of building ok 3/24/2005 9:08:12 AM
|
Electrical Rough-In | 3/15/2005 | 3/16/2005 | 3/16/2005 | A | PART |
Pat Lass
|
|
|
Contact: Lyle Dean - Underground Inspection; Phone #: ###-#### Internet Inspection Request from: Deb McCoy
partial u/G ok 3/16/2005 10:31:12 AM
|