Final | 10/26/2005 | 10/27/2005 | 10/27/2005 | A | PASS |
Mike Kinnear
|
|
|
ok final no card on site
|
Final | 9/29/2005 | 9/30/2005 | 9/30/2005 | P | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 9/29/2005 at 11:45:43 AM. Contact: ###-####. ok final all runway wire & lights are ELT certified
|
Electrical Rough-In | 8/1/2005 | 8/1/2005 | 8/1/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 8/1/2005 at 11:28:23 AM. Contact: ###-####.ok cover under ground anop
|
Electrical Rough-In | 7/28/2005 | 7/29/2005 | 7/29/2005 | P | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 7/28/2005 at 3:41:50 PM. Contact: ###-####. ok cover anop
|
Electrical Rough-In | 7/28/2005 | 7/28/2005 | 7/28/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 7/28/2005 at 8:55:14 AM. Contact: ###-####. ok cover under ground anop
|
Electrical Rough-In | 7/12/2005 | 7/13/2005 | 7/13/2005 | P | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 7/12/2005 at 9:48:45 AM. Contact: ###-####. ok cover anop
|
Electrical Rough-In | 7/6/2005 | 7/6/2005 | 7/6/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 7/6/2005 at 9:19:23 AM. Contact: ###-####. ok cover under ground anop
|
Electrical Rough-In | 6/30/2005 | 7/1/2005 | 7/1/2005 | P | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/30/2005 at 11:20:59 AM. Contact: ###-####. ok cover duct bank anop
|
Electrical Rough-In | 6/28/2005 | 6/29/2005 | 6/29/2005 | A | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/28/2005 at 11:31:30 AM. Contact: ###-####. ok cover undeground duct bank anop
|
Electrical Rough-In | 6/24/2005 | 6/24/2005 | 6/24/2005 | P | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 6/24/2005 at 10:21:04 AM. Contact: ###-####. ok anop
|
Electrical Rough-In | 6/21/2005 | 6/22/2005 | 6/22/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/21/2005 at 3:15:34 PM. Contact: ###-####. ok cover underground duct bank anop
|
Conference | 6/20/2005 | 6/21/2005 | 6/21/2005 | P | PASS |
Jim Schmer
|
|
|
tony ###-#### Met with engineers, elec. cont. and air port personal - ok jms
|
Electrical Rough-In | 6/21/2005 | 6/21/2005 | 6/21/2005 | P | PASS |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/21/2005 at 10:11:20 AM. Contact: ###-####. ok cover duct blank anop
|
Conference | 6/20/2005 | 6/21/2005 | 6/21/2005 | P | PASS |
Mike Kinnear
|
|
|
324 & 412 had meeting with washington group rick deters,alex mckean, & markus g. green
|
Electrical Rough-In | 6/18/2005 | 6/20/2005 | 6/20/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/18/2005 at 8:12:48 AM. Contact: ###-####. ok cover duct bank anop
|
Electrical Rough-In | 6/16/2005 | 6/16/2005 | 6/16/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/16/2005 at 7:12:27 AM. Contact: ###-####. ok cover underground anop all east west duct bank completed
|
Electrical Rough-In | 6/14/2005 | 6/15/2005 | 6/15/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/14/2005 at 12:07:21 PM. Contact: ###-####. ok cover part underr ground anop
|
Electrical Rough-In | 6/10/2005 | 6/13/2005 | 6/13/2005 | P | NR |
Mike Kinnear
|
|
|
tony; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles this job not ready looked at ele05-01718
|
Electrical Rough-In | 6/9/2005 | 6/10/2005 | 6/10/2005 | P | CANC |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/9/2005 at 3:16:46 PM. Contact: ###-####. t/w tony he canc. inspection
|
Electrical Rough-In | 6/8/2005 | 6/9/2005 | 6/9/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/8/2005 at 6:04:56 PM. Contact: ###-####. ok cover anop
|
Electrical Rough-In | 6/7/2005 | 6/8/2005 | 6/8/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/7/2005 at 7:09:14 PM. Contact: ###-####. ok cover anop
|
Electrical Rough-In | 6/7/2005 | 6/7/2005 | 6/7/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/7/2005 at 7:43:28 AM. Contact: ###-####. ok cover anop
|
Electrical Rough-In | 6/6/2005 | 6/6/2005 | 6/6/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/6/2005 at 10:44:44 AM. Contact: ###-####. ok cover anop
|
Electrical Rough-In | 6/2/2005 | 6/3/2005 | 6/3/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/2/2005 at 5:29:29 PM. Contact: ###-####. ok cover under ground duct bank asop
|
Electrical Rough-In | 6/1/2005 | 6/2/2005 | 6/2/2005 | P | PART |
Mike Kinnear
|
|
|
Scheduled by a contractor via Hello! on 6/1/2005 at 5:20:18 PM. Contact: ###-####. ok cover duct bank anop
|
Electrical Rough-In | 5/27/2005 | 5/31/2005 | 5/31/2005 | P | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 5/27/2005 at 4:10:49 PM. Contact: ###-####. anop mike and jack
|
Electrical Rough-In | 5/26/2005 | 5/27/2005 | 5/27/2005 | A | PART |
Mike Kinnear
|
|
|
tony; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok cover duct bank as marked on print about 400 lft
|