Final | 10/16/2006 | 10/17/2006 | 10/17/2006 | A | PASS |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 10/16/2006 at 12:24:14 PM. Contact: ###-####.
|
Final | 10/3/2006 | 10/4/2006 | 10/4/2006 | A | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 10/3/2006 at 1:18:04 PM. Contact: ###-####. signed T/I several GFCIs not working broken flex by chiller over fused fan unit in it room cord through ceiling for heater on first floor bond around dielectrics
|
Electrical Rough-In | 8/31/2006 | 9/1/2006 | 9/1/2006 | A | PASS |
Pat Lass
|
|
|
###-####. Scheduled by a contractor via Hello! on 8/31/2006 at 12:35:56 PM. Contact: ###-####. all ceilings ok
|
Electrical Rough-In | 8/16/2006 | 8/17/2006 | 8/17/2006 | A | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 8/16/2006 at 12:40:52 PM. Contact: ###-####. 3rd floor ceiling ANOP
|
Electrical Rough-In | 8/15/2006 | 8/16/2006 | 8/16/2006 | A | FAIL |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 8/15/2006 at 1:27:41 PM. Contact: ###-####. 3rd floor ceiling has open boxes and missing supports throughout
|
Electrical Rough-In | 7/21/2006 | 7/24/2006 | 7/24/2006 | A | PART |
Pat Lass
|
|
|
overhead inspection for cover//dave; Phone #: ###-#### Internet Inspection Request from: Letitia Gallop 1st and 2nd floor ceilings anop
|
Electrical Rough-In | 6/22/2006 | 6/23/2006 | 6/23/2006 | A | PASS |
Pat Lass
|
|
|
Rough-in inspection for third floor walls. Contact is Dave ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Steve Syltie 3rd floor walls ok ANOP
|
Electrical Rough-In | 6/15/2006 | 6/16/2006 | 6/16/2006 | A | PART |
Pat Lass
|
|
|
rough-in inspection for the first and second floor rest rooms. Contact is Dave @ ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Steve Syltie bathroom hard lids 1st and 2nd floors ANOP
|
Electrical Rough-In | 6/6/2006 | 6/7/2006 | 6/7/2006 | A | PART |
Pat Lass
|
|
|
Rough-in for first & third floor walls. Contact Dave @ ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Steve Syltie entire first floor walls ok half of third floor walls ok anop
|
Electrical Rough-In | 6/2/2006 | 6/2/2006 | 6/2/2006 | P | PART |
Pat Lass
|
|
|
Rough-in on first floor walls. Please call Dave when you arrive. ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Steve Syltie walls ANOP on 1st floor
|
Electrical Rough-In | 5/25/2006 | 5/26/2006 | 5/26/2006 | A | PASS |
Jim Schmer
|
|
|
Rough-in on 2nd Floor. Contact is Dave ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Steve Syltie walls only JMS
|
Electrical Rough-In | 5/5/2006 | 5/8/2006 | 5/8/2006 | A | PART |
Pat Lass
|
|
|
3RD FLOOR PARTIAL ROUGH-IN INSPECTION. CONTACT IS DAVE @ ###-####. THANKS; Phone #: ###-#### Internet Inspection Request from: Steve Syltie 3rd floor ANOP
|
Electrical Rough-In | 4/27/2006 | 4/28/2006 | 4/28/2006 | A | PART |
Pat Lass
|
|
|
Contact is Dave Tolan. ###-####. Need to inspect the underfloor system for cover.; Phone #: ###-#### Internet Inspection Request from: Steve Syltie Under floor power ANOP on 2nd floor another contractor will be doing control under floor
|
Electrical Rough-In | 4/20/2006 | 4/21/2006 | 4/21/2006 | A | PART |
Pat Lass
|
|
|
Wall inspection for cover. Also consult on service. Contact is Dave Tolan ###-####. Thanks.; Phone #: ###-#### Internet Inspection Request from: Steve Syltie partial for some walls on first and second floors ok ANOP
|
Electrical Rough-In | 3/28/2006 | 3/29/2006 | 3/29/2006 | P | PASS |
William E Thomas
|
|
|
NEED ROOF ROUGH-IN AND CONSULTATION. DAVE TOLIN ###-####.; Phone #: ###-#### Internet Inspection Request from: Steve Syltie roof parapet ok
|
ELE-Aging Inspection | 3/22/2006 | 3/22/2006 | 3/23/2006 | | NR |
Pat Lass
|
|
|
no R/I for building yet suc
|
Electrical Rough-In | 1/18/2006 | 1/18/2006 | 1/18/2006 | P | PART |
Bob Reichert
|
|
|
Underground inspection. Thanks.; Phone #: ###-#### Internet Inspection Request from: Steve Syltie u/g first fl computer fl ok to cover
|
Electrical Rough-In | 10/25/2005 | 10/25/2005 | 10/25/2005 | P | PASS |
William E Thomas
|
|
|
Remainder of parking lot underground will be ready this afternoon.; Phone #: ###-#### Internet Inspection Request from: Steve Syltie underground ok
|
Electrical Rough-In | 10/24/2005 | 10/24/2005 | 10/24/2005 | P | PART |
Pat Lass
|
|
|
This is for the underground conduits in the parking lot. Parking lot is west of main building across the street.; Phone #: ###-#### Internet Inspection Request from: Steve Syltie all but the east feed to the lot is ok. east end feed not ready.
|