Final | 4/12/2006 | 4/12/2006 | 4/12/2006 | P | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 4/12/2006 at 7:42:25 AM. Contact: ###-####. met elect checked out work because exst power is connected, ok to final
|
Permanent Service | 4/12/2006 | 4/12/2006 | 4/12/2006 | P | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 4/12/2006 at 7:41:24 AM. Contact: ###-####. p/s u/g n ok
|
Electrical Rough-In | 2/27/2006 | 2/27/2006 | 2/27/2006 | P | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 2/27/2006 at 10:46:57 AM. Contact: ###-####. ric ok, corr made
|
Electrical Rough-In | 2/24/2006 | 2/27/2006 | 2/27/2006 | A | NR |
Pat Lass
|
|
|
don ###-#### grounds not made up and not yet nailplated
|