Final | 6/8/2006 | 6/8/2006 | 6/8/2006 | P | PASS |
Bob Reichert
|
|
|
Call Mike w/ Doherty @ ###-#### for questions. Scheduled by Heather w/ Doherty; Phone #: ###-#### Internet Inspection Request from: Heather Packer ok to final, signed occ card
|
Final | 6/8/2006 | 6/9/2006 | 6/8/2006 | A | CANC |
Bob Reichert
|
|
|
Re-insp. Call Mike w/ Doherty @ ###-#### for questions. Scheduled by Heather w/ Doherty.; Phone #: ###-#### Internet Inspection Request from: Heather Packer Inspection cancelled from web by: Heather Packer
|
Final | 6/7/2006 | 6/7/2006 | 6/7/2006 | P | NR |
Bob Reichert
|
|
|
For questions please call Mike w/ Doherty @ ###-####. Scheduled by Heather w/ Doherty; Phone #: ###-#### Internet Inspection Request from: Heather Packer talked to contr, needs to provide disc for hw heater, bond h&c pipes, loose recpts by cooler and bath, add gfci to cash register recpt, add covers painters took off, add cond strap, add bkr numbers
|
Permanent Service | 5/26/2006 | 5/26/2006 | 5/26/2006 | P | PASS |
Bob Reichert
|
|
|
Questions call Mike @ ###-#### - scheduled by Heather Packer w/ Doherty; Phone #: ###-#### Internet Inspection Request from: Heather Packer p/s exst meter pak, n ok
|
Electrical Rough-In | 4/19/2006 | 4/19/2006 | 4/19/2006 | P | PASS |
Bob Reichert
|
|
|
re-insp. for ceiling - there is access now - sorry -call Chris for questions ###-#### or Mike ###-#### scheduled by Heather w/ Doherty; Phone #: ###-#### Internet Inspection Request from: Heather Packer ok to cover ceiling, corr made
|
Electrical Rough-In | 4/18/2006 | 4/19/2006 | 4/19/2006 | A | NH |
Bob Reichert
|
|
|
Ceiling inspection - scheduled by Heather Packer w/ Doherty ; Phone #: ###-#### Internet Inspection Request from: Heather Packer called left card said to call when someone there
|
Electrical Rough-In | 4/17/2006 | 4/18/2006 | 4/18/2006 | A | FAIL |
Bob Reichert
|
|
|
Ceiling insp. - as early as possible - scheduled by Heather Packer w/ Doherty; Phone #: ###-#### Internet Inspection Request from: Heather Packer called left message, left corr notice, 300.11(A) cables shall not be supported by ceiling grid unless tested as part of fire rated assembly, 725.8 class 1,2,3 cables shall be supported by straps,staples, hangars or similar fittings designed to not damage cable, 800.24 communications cables shall be installed by fittings so as to not damage cable
|
Electrical Rough-In | 3/31/2006 | 3/31/2006 | 3/31/2006 | P | PART |
Bob Reichert
|
|
|
Phone #: ###-#### Internet Inspection Request from: Heather Packer u/g ok to use, ceiling not ready, will recall
|
Electrical Rough-In | 3/22/2006 | 3/24/2006 | 3/24/2006 | A | PART |
Bob Reichert
|
|
|
RI partial walls. Thanks!; Phone #: ###-#### Internet Inspection Request from: Heather Packer met contr, left corr notice, 110.26(F)(1)(a) the space equal to the width and depth of the equipment and extending from the floor to the structural ceiling shall be dedicated to the electrical installation, BCC u/g shall be inspected before cover, interior walls except at panel area ok to cover anop
|
Electrical Rough-In | 3/9/2006 | 3/10/2006 | 3/10/2006 | A | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 3/9/2006 at 3:24:37 PM. Contact: ###-####. ok to cover walls anop, nw and column east
|