Final | 5/4/2007 | 5/8/2007 | 5/8/2007 | A | PASS |
Mike Kinnear
|
|
|
Ready for Final! Jason will meet Mike Kinear out there at 8:30am (per Mike) Phone #: ###-#### Internet Inspection Request from: Dan Mitchell ok final note signed card
|
ELE-Aging Inspection | 4/9/2007 | 4/9/2007 | 4/17/2007 | | NR |
Mike Kinnear
|
|
|
UL working on field evaluations
|
ELE-Aging Inspection | 1/17/2007 | 1/17/2007 | 1/24/2007 | | NR |
Mike Kinnear
|
|
|
t/w dan they got with ul & customer
|
ELE-Aging Inspection | 9/28/2006 | 9/28/2006 | 9/28/2006 | | NR |
Mike Kinnear
|
|
|
t/w dan they still working on the job
|
Final | 7/27/2006 | 7/28/2006 | 7/28/2006 | A | NR |
Mike Kinnear
|
|
|
jason; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley conf regarding grounding transformers --- listing & labling equipment & propane dispenser
|
Electrical Rough-In | 7/19/2006 | 7/20/2006 | 7/20/2006 | A | PASS |
Mike Kinnear
|
|
|
Please inspect trench from building to propane tank so we can back-fill. Thanks !!!!!!!; Phone #: ###-#### Internet Inspection Request from: Dan Mitchell ok cover under ground conduit
|
Conference | 6/27/2006 | 6/27/2006 | 6/27/2006 | P | PASS |
Mike Kinnear
|
|
|
Dan Mitchell, call him 1/2 hr. before you go; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt conf regarding propane dispencer
|
Rough-In Permanent Service | 6/9/2006 | 6/12/2006 | 6/12/2006 | A | CANC |
Mike Kinnear
|
|
|
We have trimmed out the office areas, added some new emergency lights and emergency exit signs in the office areas. We connected their new Propane Pump to the existing circuit in the northeast corner of the property. We also performed other work in the production plant areas. At this time we are only looking for a Final on the Office wiring and the emergency lights / exits, and the Propane Pump. We will schedule the inspection for the rest of the work at a future time. Thanks !!!! Dan.; Phone #: ###-#### Internet Inspection Request from: Dan Mitchell wrong type inspection
|
Final | 6/12/2006 | 6/12/2006 | 6/12/2006 | P | PART |
Mike Kinnear
|
|
|
We have trimmed out the office areas, added some new emergency lights and emergency exit signs in the office areas. We connected their new Propane Pump to the existing circuit in the northeast corner of the property. We also performed other work in the production plant areas. At this time we are only looking for a Final on the Office wiring and the emergency lights / exits, and the Propane Pump. We will schedule the inspection for the rest of the work at a future time. Thanks !!!! Dan.; Phone #: ###-#### Internet Inspection Request from: Dan Mitchell --- propane pump not ready --- ok perm occ. office area no sign off card
|
Electrical Rough-In | 4/14/2006 | 4/14/2006 | 4/14/2006 | P | PASS |
Mike Kinnear
|
|
|
Rough-in for cover. We disconnected and abandoned the romex wiring. Roughed-in some switch and receptacle wiring in the upstairs offices they are remodeling. Jman/Jason/###-#### may still be on-site when you arrive.Thanks!!! Dan. This building is next door to Sysco.; Phone #: ###-#### Internet Inspection Request from: Dan Mitchell ok cover ri ceiling & walls the outlets are cut in boxes
|