Final | 4/13/2007 | 4/16/2007 | 4/16/2007 | A | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 4/13/2007 at 1:55:57 PM. Contact: ###-####. corr made, ok to final, signed card
|
Final | 4/12/2007 | 4/13/2007 | 4/13/2007 | A | FAIL |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 4/12/2007 at 2:49:14 PM. Contact: ###-####. met elect, wrote corr notice to owner, nec 110.26, sufficient access and working space shall be provided and maintained about all electric equipment to permit ready and safe operation and maintenance of such equipment. ref. panel 1PF and other panels in elect room 2nd floor behind food court area
|
Permanent Service | 11/15/2006 | 11/16/2006 | 11/16/2006 | A | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 11/15/2006 at 7:26:36 PM. Contact: ###-####. p/s u/g n ok
|
Electrical Rough-In | 10/13/2006 | 10/13/2006 | 10/13/2006 | A | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 10/13/2006 at 7:06:44 AM. Contact: ###-####. soffit lights 2nd story ok to cover
|
Electrical Rough-In | 9/28/2006 | 9/29/2006 | 9/29/2006 | A | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 9/28/2006 at 2:09:04 PM. Contact: ###-####. ok to cover gec
|
Final | 9/26/2006 | 9/26/2006 | 9/26/2006 | P | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 9/26/2006 at 11:13:24 AM. Contact: ###-####. ok to final maintenance extension only, rest of project suc
|
Electrical Rough-In | 9/25/2006 | 9/25/2006 | 9/25/2006 | P | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 9/25/2006 at 9:03:20 AM. Contact: ###-####. u/g front lights ok to cover, main entrance hard lid ok to cover
|
Rough-In Permanent Service | 9/21/2006 | 9/22/2006 | 9/22/2006 | A | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 9/21/2006 at 2:49:53 PM. Contact: ###-####. ok to pour concrete encased electrode
|
Electrical Rough-In | 9/20/2006 | 9/20/2006 | 9/20/2006 | P | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 9/20/2006 at 7:11:46 AM. Contact: ###-####. u/g so side new bldg ok to cover, will be between bldgs
|
Electrical Rough-In | 9/13/2006 | 9/14/2006 | 9/14/2006 | A | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 9/13/2006 at 2:30:32 PM. Contact: ###-####. ok to cover u/g going north from front of bldg to swgr
|
Electrical Rough-In | 9/13/2006 | 9/13/2006 | 9/13/2006 | P | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 9/13/2006 at 10:08:24 AM. Contact: ###-####. south 1/2 u/g ok to cover at front bldg
|
Electrical Rough-In | 9/5/2006 | 9/5/2006 | 9/5/2006 | P | PART |
Bob Reichert
|
|
|
6 recessed lites in front hard lid ok to cover, talked about fixtures not being suitable for purpose for outside as requested on plans
|
Electrical Rough-In | 8/9/2006 | 8/9/2006 | 8/9/2006 | P | PASS |
Bob Reichert
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles 2 entry lights ok to cover
|
Electrical Rough-In | 7/27/2006 | 7/28/2006 | 7/28/2006 | A | PART |
Jack Frank
|
|
|
ron ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley maintance building anop
|
Electrical Rough-In | 6/19/2006 | 6/19/2006 | 6/19/2006 | P | PART |
Bob Reichert
|
|
|
pole inspection ###-#### ok to pour ,anop
|