Final | 2/15/2007 | 2/15/2007 | 2/15/2007 | A | PASS |
Mike Kinnear
|
|
|
ready for Final. outside pole lighting was the only thing left to finish. That is now complete, thank you. I beleive MIke K had allready checked the inside and exterior of building. Phone #: ###-#### ok final note no card available
|
Electrical Rough-In | 2/9/2007 | 2/12/2007 | 2/12/2007 | P | PASS |
William E Thomas
|
|
|
Call Jim for inspection on underground pole lighting conduit. please make inspection as close to 2:30pm as possible. thank you. Phone #: ###-#### 1. underground ok for cover-- pole lights.
|
Final | 12/28/2006 | 12/28/2006 | 12/28/2006 | P | PART |
Pat Lass
|
|
|
bud ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith signed T/O check heating units above bathrooms for name plates and lights and receps. GFCI protect bath receps. boxes flush in gym. fuse reducers to 60 a for RTU. heat trace on roof not done.
|
Electrical Rough-In | 12/21/2006 | 12/21/2006 | 12/21/2006 | P | PASS |
Mike Kinnear
|
|
|
Bud Note: ceiling; Phone #: ###-#### Internet Inspection Request from: Sherri Bennett ok cover ceiling only
|
Electrical Rough-In | 12/13/2006 | 12/13/2006 | 12/13/2006 | P | PART |
Mike Kinnear
|
|
|
bud - light pole bases ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith light pole bases no inspection required
|
Electrical Rough-In | 11/7/2006 | 11/8/2006 | 11/8/2006 | P | PASS |
Mike Kinnear
|
|
|
bud Note: ceiling in bathrooms; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok cover hard lid ceilings only
|
Permanent Service | 11/1/2006 | 11/2/2006 | 11/2/2006 | P | PASS |
Mike Kinnear
|
|
|
bud ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie p/s u/g n ok note IPCO has not set meter base yet will sticker it when installed
|
Rough-In Permanent Service | 10/27/2006 | 10/27/2006 | 10/27/2006 | P | PASS |
Mike Kinnear
|
|
|
Bud; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt oked 10/27/06 am by 336
|
Rough-In Permanent Service | 10/26/2006 | 10/27/2006 | 10/27/2006 | A | PART |
Pat Lass
|
|
|
bud; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles partial U/G Ok
|
Rough-In Permanent Service | 10/26/2006 | 10/27/2006 | 10/27/2006 | A | CANC |
Mike Kinnear
|
|
|
bud ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith inspection doubled
|
Electrical Rough-In | 10/25/2006 | 10/26/2006 | 10/26/2006 | A | PART |
Pat Lass
|
|
|
bud ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith walls ok
|
Electrical Rough-In | 10/3/2006 | 10/4/2006 | 10/4/2006 | A | PASS |
Mike Kinnear
|
|
|
BUD - GYM; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok cover walls only gym
|
ELE-Aging Inspection | 9/19/2006 | 9/19/2006 | 9/19/2006 | | NR |
Mike Kinnear
|
|
|
still framing
|
Electrical Rough-In | 7/20/2006 | 7/20/2006 | 7/20/2006 | P | PASS |
Mike Kinnear
|
|
|
r/i on slab-- bud; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok cover under slab conduit
|
Electrical Rough-In | 7/18/2006 | 7/18/2006 | 7/18/2006 | P | PASS |
Mike Kinnear
|
|
|
bud; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley ok cover under slab conduit in gym area
|
Rough-In Permanent Service | 7/11/2006 | 7/11/2006 | 7/11/2006 | P | PASS |
Jim Schmer
|
|
|
bud; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles main service, telephone and fire alarm conduit through the footing jms
|
Electrical Rough-In | 6/28/2006 | 6/29/2006 | 6/29/2006 | A | PASS |
Jim Schmer
|
|
|
Ufer ground inspection. Please inspect as early a.m. on 06/29 as possible. Thanks!; Phone #: ###-#### Internet Inspection Request from: Steve Syltie
|