Final | 11/20/2006 | 11/27/2006 | 11/27/2006 | A | PASS |
Mike Kinnear
|
|
|
Final inspection of building 21 remodel. Internet Inspection Request from: Del Elwood ok final
|
Final | 11/16/2006 | 11/20/2006 | 11/20/2006 | A | PASS |
Mike Kinnear
|
|
|
Final inspection of a remodel in building 21. Internet Inspection Request from: Del Elwood ok final
|
Electrical Rough-In | 10/18/2006 | 10/19/2006 | 10/19/2006 | A | PASS |
Mike Kinnear
|
|
|
Building 21 remodel ceiling rough in.; Phone #: ###-#### Internet Inspection Request from: Del Elwood ok cover ceiling only
|
Electrical Rough-In | 9/6/2006 | 9/7/2006 | 9/7/2006 | A | PASS |
Mike Kinnear
|
|
|
Rough-in inspection of building 21 remodel.; Phone #: ###-#### Internet Inspection Request from: Del Elwood ok cover walls only
|