Electrical Rough-In | 11/27/2006 | 11/27/2006 | 11/27/2006 | A | PASS |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 11/27/2006 at 7:20:53 AM. Contact: ###-####. ceiling ok
|
Final | 11/27/2006 | 11/27/2006 | 11/27/2006 | A | PASS |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 11/27/2006 at 7:20:53 AM. Contact: ###-####. ok no card
|
Permanent Service | 9/29/2006 | 9/29/2006 | 9/29/2006 | P | PASS |
Bob Reichert
|
|
|
Stu; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt p/s exst meter pak, n ok
|
Electrical Rough-In | 9/26/2006 | 9/26/2006 | 9/26/2006 | P | PASS |
Bob Reichert
|
|
|
stu; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie walls only ok to cover
|
Electrical Rough-In | 9/25/2006 | 9/25/2006 | 9/25/2006 | P | PART |
Bob Reichert
|
|
|
stu - as early as possible; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley west end and center walls only ok to cover
|
Electrical Rough-In | 9/21/2006 | 9/22/2006 | 9/22/2006 | A | PART |
Bob Reichert
|
|
|
stu - early morning if possible; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley east wall only ok to cover
|
Electrical Rough-In | 9/21/2006 | 9/22/2006 | 9/22/2006 | P | CANC |
Bob Reichert
|
|
|
nr per stu - late afternoon if possible; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|