Electrical Rough-In | 10/18/2006 | 10/19/2006 | 10/19/2006 | A | PASS |
Pat Lass
|
|
|
Business is Greenleaf Wholesale, anyone there can give you the tour.We installed a new subpanel below the existing panel in the snack/break room. Pulled 2 new 20 amp 120 volt circuits from this sub-panel through an existing 3/4" EMT to an existing j-box on the trusses. Ran a new 3/4" EMT from this j-box to a second existing j-box on top of the Tropical Cooler where we capped off the old circuit feeders and connected our 2 new circuits to the existing wires going to the computer receptacles, effectively placing the existing computer receptacles onto the 2 new dedicated circuits. Labled all 4 circuit breakers involved. Thanks!!! Tech/Dan/###-####.(6090967g); Phone #: ###-####
|
Final | 10/19/2006 | 10/19/2006 | 10/19/2006 | P | PASS |
Pat Lass
|
|
|
Business is Greenleaf Wholesale, anyone there can give you the tour.We installed a new subpanel below the existing panel in the snack/break room. Pulled 2 new 20 amp 120 volt circuits from this sub-panel through an existing 3/4" EMT to an existing j-box on the trusses. Ran a new 3/4" EMT from this j-box to a second existing j-box on top of the Tropical Cooler where we capped off the old circuit feeders and connected our 2 new circuits to the existing wires going to the computer receptacles, effectively placing the existing computer receptacles onto the 2 new dedicated circuits. Labled all 4 circuit breakers involved. Thanks!!! Tech/Dan/###-####.(6090967g); Phone #: ###-####
|