Final | 9/2/2008 | 9/2/2008 | 9/2/2008 | P | PASS |
Bob Reichert
|
|
|
Roughin for wall store fronts suites #250, #246 & #216 plus ceiling inspection for third floor bathrooms. Thank you. Phone #: ###-#### Internet Inspection Request from: Lloyd Looney ric ok storefronts 250,246,216 and 3rd floor bath ceilings
|
Electrical Rough-In | 8/14/2008 | 8/15/2008 | 8/15/2008 | A | PART |
Pat Lass
|
|
|
Bathrooms on third floor ready for cover Phone #: ###-#### Internet Inspection Request from: Lloyd Looney R/I Ok no esc in project
|
Electrical Rough-In | 8/13/2008 | 8/14/2008 | 8/14/2008 | A | NR |
Bob Reichert
|
|
|
Need third floor, new bathrooms wall roughin inspection. Phone #: ###-#### Internet Inspection Request from: Lloyd Looney met superintendent, no power rough-in for drinking fountains, called electrical contractor, told to call when ready, fee due
|
Final | 7/17/2008 | 7/18/2008 | 7/18/2008 | A | NR |
Pat Lass
|
|
|
We need finals for store fronts at suites 182 & 184, Thank you Phone #: ###-#### Internet Inspection Request from: Lloyd Looney call for final when finished I plug tested these two and that was ok but you had mc cable not terminated in a box and pipes not strraped also another permit must be taken out for each of these prior to occupancy on a t/i permit.
|
Electrical Rough-In | 7/1/2008 | 7/2/2008 | 7/2/2008 | A | PASS |
Bob Reichert
|
|
|
Store front for suit # 182 Phone #: ###-#### Internet Inspection Request from: Lloyd Looney ric ok store-front only
|
Electrical Rough-In | 6/10/2008 | 6/11/2008 | 6/11/2008 | A | PASS |
Bob Reichert
|
|
|
Suits 206 & 214 Store fronts are ready, early is OK. Phone #: ###-#### Internet Inspection Request from: Lloyd Looney store fronts only ok to cover, no esc
|
Electrical Rough-In | 6/4/2008 | 6/5/2008 | 6/5/2008 | A | PART |
Bob Reichert
|
|
|
Roughin for new store fronts on suites # 151 & 185 Phone #: ###-#### Internet Inspection Request from: Lloyd Looney ok to cover storefront for pottery (common area)
|