Final | 11/17/2009 | 11/18/2009 | 11/18/2009 | P | PASS |
Doug A Poedy
|
|
|
Strapped liquid tight flex to motors, replaced faceplates for switches. None of the outlets in this structure where done by us, assuming you are talking about the panel cover which we replaced. Just pool equipment. Stucco guys had removed everything and didn''t notify me. Thanks Phone #: ###-#### Internet Inspection Request from: Lynn Cable
|
Final | 11/16/2009 | 11/17/2009 | 11/17/2009 | P | FAIL |
Doug A Poedy
|
|
|
Pool house still under construction, Pool house door in back is usually open. Thanks Phone #: ###-#### Internet Inspection Request from: Lynn Cable. 406.5 Receptacle faceplates. NEC 404.9 A Switch faceplates. NEC 356.30 Securing and supporting.
|
Electrical Rough-In | 10/14/2009 | 10/14/2009 | 10/14/2009 | P | PASS |
Doug A Poedy
|
|
|
potting compound on pool and spa light. Pool builder is there to provide access. Are planning to start filling pool this evening. Phone #: ###-#### Internet Inspection Request from: Lynn Cable
|
Electrical Rough-In | 7/1/2008 | 7/1/2008 | 7/1/2008 | P | PASS |
William E Thomas
|
|
|
Pool Bonding and Light Niches Phone #: ###-#### Internet Inspection Request from: Lynn Cable . .1. pool bonding ok. . .
|