Final | 11/13/2008 | 11/13/2008 | 11/13/2008 | P | PASS |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 11/13/2008 at 9:52:23 AM. Contact: ###-####.
|
Final | 11/10/2008 | 11/10/2008 | 11/10/2008 | P | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 11/10/2008 at 8:05:06 AM. Contact: ###-####. checked receps etc in garage and storage check grounding at house and straps on risers and smerf
|
Permanent Service | 11/6/2008 | 11/7/2008 | 11/7/2008 | A | PASS |
Pat Lass
|
|
|
cyrille- call 1st before insp Phone #: ###-#### P/S U/G R Ok for power check feed to house next inspection.
|
Conference | 11/6/2008 | 11/6/2008 | 11/6/2008 | P | CANC |
Pat Lass
|
|
|
cyrille Phone #: ###-#### service not covered under this permit
|
Electrical Rough-In | 10/6/2008 | 10/7/2008 | 10/7/2008 | P | PASS |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 10/6/2008 at 5:11:40 PM. Contact: ###-####.
|
Electrical Rough-In | 10/3/2008 | 10/6/2008 | 10/6/2008 | A | FAIL |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 10/3/2008 at 7:20:55 PM. Contact: ###-####. not ready, needs bond screw, install wire under acorn between the clamp and the rod, complete all makeup, use UF cable in u/g conduit met owner
|
Conference | 9/9/2008 | 9/10/2008 | 9/10/2008 | A | DONE |
Jack Frank
|
|
|
CYRILLE NOTE: PLEASE CALL 1/2 HR PRIOR TO INSPECTION Phone #: ###-#### ok
|
Conference | 8/21/2008 | 8/21/2008 | 8/21/2008 | P | PART |
Pat Lass
|
|
|
call 1st before insp cyrille Phone #: ###-#### talked about general requirements
|