Final | 10/2/2008 | 10/3/2008 | 10/3/2008 | A | PASS |
Mike Kinnear
|
|
|
Please provide final inspection - Contact Steve Harris ###-#### Phone #: ###-#### Internet Inspection Request from: Kevin Perez ok final note no esc permit in project
|
Final | 10/2/2008 | 10/2/2008 | 10/2/2008 | P | FAIL |
Mike Kinnear
|
|
|
Request final inspection this afternoon - Steve Harris Mountain Power Phone #: ###-#### Internet Inspection Request from: Kevin Perez t/w kevin permit is not grouped with BLD permit advised him to t/w rita deyoung & correct this. then call for final inspection
|
Electrical Rough-In | 9/16/2008 | 9/16/2008 | 9/16/2008 | P | PASS |
Pat Lass
|
|
|
US Bank Building Volt TI 4th Floor. Need rough-in ceiling inspection either this afternoon or tomorrow morning. field Electrician Steve Harris Cell ###-#### Phone #: ###-#### Internet Inspection Request from: Kevin Perez
|
Electrical Rough-In | 8/26/2008 | 8/26/2008 | 8/26/2008 | P | PASS |
Pat Lass
|
|
|
Loren Phone #: ###-#### 4th floor walls ok
|