Final | 1/21/2009 | 1/22/2009 | 1/22/2009 | A | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 1/21/2009 at 7:10:49 AM. Contact: ###-####. ok to final, signed occupancy card, no esc this project
|
Electrical Rough-In | 1/19/2009 | 1/20/2009 | 1/20/2009 | A | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 1/19/2009 at 7:08:21 AM. Contact: ###-####. ceilings 3rd floor phase #2 anop
|
Electrical Rough-In | 1/6/2009 | 1/7/2009 | 1/7/2009 | A | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 1/6/2009 at 6:14:34 AM. ok to cover ceiling 2nd floor anop, no esc this project
|
Final | 1/7/2009 | 1/7/2009 | 1/7/2009 | A | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 1/6/2009 at 6:14:34 AM. ok to final rooms 2nd floor anop no esc this project
|
Electrical Rough-In | 12/31/2008 | 12/31/2008 | 12/31/2008 | P | PART |
Jack Frank
|
|
|
Phone #: ###-#### 3rd floor ceilings anop
|
Electrical Rough-In | 12/23/2008 | 12/24/2008 | 12/24/2008 | A | PART |
Jack Frank
|
|
|
Scheduled by a contractor via Hello! on 12/23/2008 at 9:08:02 AM. Contact: ###-####.walls in 4 rms 3rd floor anop
|
Final | 12/19/2008 | 12/19/2008 | 12/19/2008 | P | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 12/19/2008 at 7:34:45 AM. ok to final rooms 2nd floor anop, no esc this project
|
Electrical Rough-In | 12/15/2008 | 12/17/2008 | 12/17/2008 | A | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 12/15/2008 at 7:53:11 AM. Contact: ###-####. walls and ceiling ok to cover anop, no esc this project
|
Electrical Rough-In | 12/3/2008 | 12/3/2008 | 12/3/2008 | A | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 12/3/2008 at 6:34:32 AM. Contact: ###-####. 3rd floor ceiling and walls only anop ok to cover, no esc this project
|
Electrical Rough-In | 11/25/2008 | 11/26/2008 | 11/26/2008 | P | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 11/25/2008 at 10:41:44 AM. Contact: ###-####. ric ok anop, no esc this project
|
Electrical Rough-In | 11/12/2008 | 11/12/2008 | 11/12/2008 | A | PASS |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 11/12/2008 at 7:18:54 AM. Contact: ###-####. walls only anop 3rd floor, no esc this project
|
Electrical Rough-In | 11/3/2008 | 11/4/2008 | 11/4/2008 | P | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 11/3/2008 at 2:17:46 PM. Contact: ###-####. walls only anop ok to cover, 3rd floor, no esc this project
|
Electrical Rough-In | 10/24/2008 | 10/27/2008 | 10/27/2008 | A | PART |
Pat Lass
|
|
|
Scheduled by a contractor via Hello! on 10/24/2008 at 1:25:53 PM. Contact: ###-####. no esc in project ando walls
|
Electrical Rough-In | 10/23/2008 | 10/23/2008 | 10/23/2008 | P | PART |
Bob Reichert
|
|
|
Scheduled by a contractor via Hello! on 10/23/2008 at 7:41:58 AM. Contact: ###-####. ok to cover walls and ceilings anop, no esc this project
|