Temporary Service | 6/17/2009 | 6/18/2009 | 6/18/2009 | A | PASS |
Jack Frank
|
|
|
We have completed teh installation of the Temporary Power and Idaho Power will be making the final connections 6/17/09 am. Phone #: ###-#### Internet Inspection Request from: Clint Tate t/s u/g new ok
|
Rough-In Permanent Service | 6/16/2009 | 6/16/2009 | 6/16/2009 | P | CANC |
Jack Frank
|
|
|
Please inspect the Underground and we will call in for the final when we have access to teh Transformer to make the final connections. If we do not need ot have these connected please perform a Permanant Service inspection so we can get the power turned on and set up. Thank you. Phone #: ###-#### Internet Inspection Request from: Clint Tate see added t/s
|
Temporary Service | 6/16/2009 | 6/16/2009 | 6/16/2009 | P | PART |
Jack Frank
|
|
|
Phone #: ###-#### Internet Inspection Request from: Clint Tate t/s u/g new ok for power no final on permit
|