Final | 9/1/2009 | 9/2/2009 | 9/2/2009 | P | PASS |
Bob Reichert
|
|
|
Please provide final inspection. Phone #: ###-#### Internet Inspection Request from: Spencer Mclean checked babana area, ok to final, no esc this project
|
Electrical Rough-In | 7/9/2009 | 7/9/2009 | 7/9/2009 | P | PART |
Doug A Poedy
|
|
|
Inspected banana room roof. Found control panels to be UL listed with diagrams. Wiring was not complete. Also inspected building rooftop conduit racks for Mclean Electrics section and it looked good. Mike Kinnear inspected Inside banana room and door openers,and found openers not to be UL listed.
|
Electrical Rough-In | 7/7/2009 | 7/9/2009 | 7/9/2009 | P | PART |
Mike Kinnear
|
|
|
Please provide a rough-in inspection on the Banana Room. Tye is your contact. Phone #: ###-#### Internet Inspection Request from: Spencer Mclean correction B.C.C.4-05-33(A) all electrical equipment shall listed & so labled by an approved testing laboratory. note we have not completed the inspections regarding this permit
|