Final | 4/20/2010 | 4/20/2010 | 4/20/2010 | P | PASS |
Bob Reichert
|
|
|
Mark ###-#### ok to final, signed card, no esc this project
|
Electrical Rough-In | 3/29/2010 | 3/30/2010 | 3/30/2010 | A | PASS |
Bob Reichert
|
|
|
Please Call To Meet Desk ###-#### Cell ###-#### Inspection requested from web by: mark morris Phone #: ###-#### ok to cover hard lid only, no esc this project
|
Electrical Rough-In | 3/25/2010 | 3/26/2010 | 3/26/2010 | A | CANC |
Bob Reichert
|
|
|
Please call to meet
Desk ###-####
Cell ###-#### Inspection requested from web by: mark morris Phone #: ###-#### Inspection cancelled from web by: mark morris
|
Electrical Rough-In | 3/17/2010 | 3/17/2010 | 3/17/2010 | P | PART |
Doug A Poedy
|
|
|
please call to meet cell ###-#### desk ###-#### Inspection requested from web by: mark morris Phone #:###-####. 3rd floor
|
ELE-Aging Inspection | 3/15/2010 | 3/15/2010 | 3/15/2010 | | DONE |
Doug A Poedy
|
|
|
Still under construction
|