Final | 8/9/2010 | 8/9/2010 | 8/9/2010 | P | PASS |
Jack Frank
|
|
|
Please see Pat (###-####) on-site to perform the Final inspection please. Thank you. Phone #: ###-#### >> Inspection requested via web by Clint Tate
|
Electrical Rough-In | 7/6/2010 | 7/6/2010 | 7/6/2010 | P | PASS |
Bob Reichert
|
|
|
Please inspect the ceiling for cover. Our Wireman on site is Pat at ###-####. Thank you. Inspection requested from web by: Clint Tate Phone #: ###-#### ceiling only ok to cover
|
Rough-In Permanent Service | 6/16/2010 | 6/16/2010 | 6/16/2010 | P | PASS |
Jack Frank
|
|
|
Please see Pat Thomas (###-####) on-site for the inspection of the Service. Thank you. Inspection requested from web by: Clint Tate Phone #: ###-#### p/s u/g new ok
|
Electrical Rough-In | 6/1/2010 | 6/1/2010 | 6/1/2010 | P | PASS |
Doug A Poedy
|
|
|
We would like to have a Wall Rough-In this afternoon please. Our Wireman on-site is Pat at ###-####. Thank you. Inspection requested from web by: Clint Tate Phone #: ###-####.
|
Electrical Rough-In | 4/26/2010 | 4/27/2010 | 4/27/2010 | A | PASS |
Bob Reichert
|
|
|
Underground Inspection requested from web by: Clint Tate Phone #: ###-#### u/g to dispensers ok
|
Electrical Rough-In | 4/21/2010 | 4/22/2010 | 4/22/2010 | A | PART |
Jack Frank
|
|
|
Inspection requested from web by: Clint Tate Phone #: ###-#### u/g fuel area
|
Conference | 4/6/2010 | 4/6/2010 | 4/6/2010 | P | DONE |
Jack Frank
|
|
|
Please see our Wireman Pat Thomas on-site. He can be reached at ###-####. He would like to have a Conference today. Thank you. Inspection requested from web by: Clint Tate Phone #: ###-####
|
Electrical Rough-In | 3/22/2010 | 3/23/2010 | 3/23/2010 | A | PASS |
Jack Frank
|
|
|
We need an Underground Inspection at this location. Please contact our Wireman at ###-#### (Pat). Thank you Inspection requested from web by: Clint Tate Phone #: ###-#### u/g N E corner ok
|
Electrical Rough-In | 2/8/2010 | 2/8/2010 | 2/8/2010 | P | PART |
Doug A Poedy
|
|
|
Pat Thomas requested underground inspection for this afternoon. Phone #: ###-#### Internet Inspection Request from: Clint Tate. Underground light poles in front.
|
Electrical Rough-In | 1/20/2010 | 1/20/2010 | 1/20/2010 | P | PART |
Bob Reichert
|
|
|
Please inspect the Underground for cover. Wireman on-site is Pat at ###-####. Thank you. Phone #: ###-#### Internet Inspection Request from: Clint Tate ok to cover u/g anop
|
Electrical Rough-In | 1/15/2010 | 1/19/2010 | 1/19/2010 | A | PART |
Bob Reichert
|
|
|
Please inspect the Undergound for Cover. Wireman on site is Pat at ###-####. Thank you Phone #: ###-#### Internet Inspection Request from: Clint Tate u/g anop ok to cover
|
Electrical Rough-In | 12/3/2009 | 12/3/2009 | 12/3/2009 | P | PASS |
Bob Reichert
|
|
|
Please see our wireman Pat Thomas at ###-#### for a Upher Ground inspection Phone #: ###-#### Internet Inspection Request from: Clint Tate ok to pour concrete encased electrode
|