Final | 8/26/2010 | 8/27/2010 | 8/27/2010 | A | PASS |
Jack Frank
|
|
|
we would at least like a temp so the customer can move in furniture tomorrow. a final would even be better thanks contact Corey on site. Phone #: ###-#### >> Inspection requested via web by Don Lustig ok card signed
|
Electrical Rough-In | 8/18/2010 | 8/19/2010 | 8/19/2010 | A | PASS |
Jack Frank
|
|
|
ceiling cover is needed please get with corey on site for areas thanks Phone #: ###-#### >> Inspection requested via web by Don Lustig
|
Electrical Rough-In | 7/29/2010 | 7/30/2010 | 7/30/2010 | P | PASS |
Jack Frank
|
|
|
this is for ceiling cover in the hard lids corey is on site Phone #: ###-#### >> Inspection requested via web by Don Lustig
|
Rough-In Permanent Service | 7/27/2010 | 7/27/2010 | 7/27/2010 | P | PASS |
Doug A Poedy
|
|
|
we just need a service inspection to order two meters corey is on site Phone #: ###-#### >> Inspection requested via web by Don Lustig. P/S Connect ok on space 140 L1 and L2
|
Electrical Rough-In | 7/20/2010 | 7/20/2010 | 7/20/2010 | A | PASS |
Doug A Poedy
|
|
|
Phone #: ###-#### >> Inspection requested via web by Don Lustig. Walls ok.
|