Final | 3/10/2011 | 3/10/2011 | 3/10/2011 | P | PASS |
Bob Reichert
|
|
|
reinspect Phone #: ###-#### >> Inspection requested via web by chris burke ok final
|
Final | 3/9/2011 | 3/10/2011 | 3/10/2011 | A | NH |
Bob Reichert
|
|
|
Phone #: ###-#### >> Inspection requested via web by chris burke called, left message, left card, fee due
|
Permanent Service | 2/1/2011 | 2/1/2011 | 2/1/2011 | P | PASS |
Bob Reichert
|
|
|
Chris Phone #: ###-#### corrections made, p/s o/h n ok
|
Electrical Rough-In | 1/18/2011 | 1/18/2011 | 1/18/2011 | P | PASS |
Doug A Poedy
|
|
|
Gave pre approval for cover, so they could sheetrock over weekend.
|
Electrical Rough-In | 1/14/2011 | 1/18/2011 | 1/18/2011 | A | FAIL |
Doug A Poedy
|
|
|
Chris Phone #: ###-#### called, walls covered, told electrical contractor to have builder open up and recall
|
Electrical Rough-In | 1/14/2011 | 1/14/2011 | 1/14/2011 | P | FAIL |
Bob Reichert
|
|
|
R/I on garage and service8-Inspect between 2 and 3 if possible--Chris Phone #: ###-#### saw contractor, left correction notice, NEC 300.4(D) edge of cable shall be 1/14" from edge of framing member, 334.23 shall protect cables within 6' of attic access, 250.50 shall connect service to concrete encased electrode, check grounding for house next trip
|
Electrical Rough-In | 12/14/2010 | 12/14/2010 | 12/14/2010 | P | PASS |
Bob Reichert
|
|
|
>> Inspection requested via web by chris burke ri ok, called to have contractor change to 11 rooms, post job id sticker and address on house,
|
Electrical Rough-In | 11/9/2010 | 11/9/2010 | 11/9/2010 | P | PASS |
Bob Reichert
|
|
|
Cover inspection for trenches only will be ready around 10:00 am Phone #: ###-#### >> Inspection requested via web by chris burke u/g ok, both sides
|