Final | 4/27/2011 | 4/27/2011 | 4/27/2011 | A | PASS |
Jack Frank
|
|
|
final for p/s
|
ELE-Aging Inspection | 4/27/2011 | 4/27/2011 | 4/27/2011 | | DONE |
Jack Frank
|
|
|
|
Permanent Service | 2/22/2011 | 2/23/2011 | 2/22/2011 | A | PASS |
Jack Frank
|
|
|
"Ryan" is contact. Thank you Phone #: ###-#### >> Inspection requested via web by Chris Chesnut p/s u/g new ok
|
Conference | 2/22/2011 | 2/22/2011 | 2/22/2011 | P | DONE |
Jack Frank
|
|
|
"Ryan" is contact. Thank you Phone #: ###-#### >> Inspection requested via web by Chris Chesnut needs all grding and bonding done at service, remove grd from subpanel, isolate grds and neutrals at subpanel p/s tagged so pipes don't freeze
|