Final | 5/26/2011 | 5/27/2011 | 5/27/2011 | A | PASS |
Bob Reichert
|
|
|
Call Nick at ###-#### to inspect power stations in locomotive shop. Far south east building. Preferably late morning if possible. Tell gate guard your boise city inspector for Mountain Power. They should let you right in. Thanks Loren Phone #: ###-#### >> Inspection requested via web by Loren Ramsey ok final
|
Electrical Rough-In | 5/11/2011 | 5/12/2011 | 5/12/2011 | A | PASS |
Bob Reichert
|
|
|
Please inpsect U.G. in Locomotive shop. It is the far South East building. 2" PVC extended on down for station power with a bare #4 copper grounding electrode conductor extended down the trench for mini power zones (transformers). Call Loren 1/2 before. I am not on site. Thanks Phone #: ###-#### >> Inspection requested via web by Loren Ramsey ri ok for u/g
|
Electrical Rough-In | 3/13/2011 | 3/14/2011 | 3/14/2011 | A | PASS |
Bob Reichert
|
|
|
Call Loren 1 hr before for inspection of underslab electrical in Locomotive shop. Loco shop is in far S/E corner of facility. Call Loren ahead as I am not on site today. Thanks Phone #: ###-#### >> Inspection requested via web by Loren Ramsey u/g ok cover
|