Electrical Rough-In | 4/26/2011 | 4/27/2011 | 4/27/2011 | A | PASS |
Bob Reichert
|
|
|
COntact is Jake Chouinard ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Campbell ri ok
|
Temporary Service | 4/27/2011 | 4/27/2011 | 4/27/2011 | A | PASS |
Bob Reichert
|
|
|
COntact is Jake Chouinard ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Campbell corrections made, t/s o/h n ok
|
Temporary Service | 4/21/2011 | 4/21/2011 | 4/21/2011 | P | FAIL |
Bob Reichert
|
|
|
Service inspection request-contact is Jake Chouinard ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Campbell met with contractor, gave corrections, add bond bushings, phase tape and color, length of neutral conductor for parallel conductors, fuse sizes
|
Electrical Rough-In | 4/19/2011 | 4/19/2011 | 4/19/2011 | P | PASS |
Bob Reichert
|
|
|
Underground inspection - contact is Jake Chouinard ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Campbell ok cover u/g upper area into pit
|
Electrical Rough-In | 4/15/2011 | 4/15/2011 | 4/15/2011 | P | CANC |
Bob Reichert
|
|
|
Underground inspection for temporary power - job site contact is Jake Chouinard, ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Campbell see conf
|
Conference | 4/15/2011 | 4/15/2011 | 4/15/2011 | P | DONE |
Bob Reichert
|
|
|
Underground inspection for temporary power - job site contact is Jake Chouinard, ###-#### Phone #: ###-#### >> Inspection requested via web by Scott Campbell met contractor, reviewed temp power, conduit spacing for u/g, pull box requirements
|