Final | 12/9/2011 | 12/9/2011 | 12/9/2011 | P | PASS |
Daryl DeGrange
|
|
|
Ryan is contact. final thank you Phone #: ###-#### >> Inspection requested via web by Chris Chesnut final ok
|
Electrical Rough-In | 10/3/2011 | 10/4/2011 | 10/4/2011 | A | PASS |
Daryl DeGrange
|
|
|
For basement rough in only. They were undecided if they were going to finish it at this time and decided to do so. Thanks, contact name is Ryan. Phone #: ###-#### >> Inspection requested via web by Chris Chesnut rough-in ok cover basement
|
Rough-In Permanent Service | 9/22/2011 | 9/23/2011 | 9/23/2011 | P | PASS |
Daryl DeGrange
|
|
|
Ryan is contact. The outlets for pass through are going to be in the bottom of uppers and outlets WILL be within 18" of counter top. (I discussed it with Jack). Thank you Phone #: ###-#### >> Inspection requested via web by Chris Chesnut rough-in p/s o/h rec ok cover 1st-2nd-3rd floors of main house unattached garage-2nd floor No basement cover of main house at this time
|
Rough-In Permanent Service | 9/21/2011 | 9/22/2011 | 9/22/2011 | A | NR |
Jack Frank
|
|
|
contact is Ryan. Thank you Phone #: ###-#### >> Inspection requested via web by Chris Chesnut address #14 on 20 amp circuit media rm, address countertop recepts pass through counter, needs recepts 2ft wall NW 2nd floor bed rm
|
Electrical Rough-In | 7/1/2011 | 7/5/2011 | 7/5/2011 | A | PASS |
Daryl DeGrange
|
|
|
ufer ground inspection in footing. Thank you. Contact name is Chris Phone #: ###-#### >> Inspection requested via web by Chris Chesnut rough-in ok concrete encased electrode
|
Electrical Rough-In | 7/1/2011 | 7/1/2011 | 7/1/2011 | P | PASS |
Daryl DeGrange
|
|
|
rough-in ok (2) concrete encased electrodes, one in house foundation and one in unattached garage foundation
|