Final | 12/4/2011 | 12/5/2011 | 12/5/2011 | A | PASS |
Jack Frank
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kevin Burke ok card signed
|
Electrical Rough-In | 11/16/2011 | 11/16/2011 | 11/16/2011 | A | PASS |
Jack Frank
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kevin Burke ceilings ok
|
Permanent Service | 10/4/2011 | 10/5/2011 | 10/5/2011 | A | PASS |
Jack Frank
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kevin p/s u/g new ok
|
Electrical Rough-In | 9/21/2011 | 9/22/2011 | 9/22/2011 | A | DONE |
Jack Frank
|
|
|
Phone #: ###-#### >> Inspection requested via web by Kevin Burke conference with contactor and owner show window recepts
|
Electrical Rough-In | 9/21/2011 | 9/21/2011 | 9/21/2011 | P | PASS |
Jack Frank
|
|
|
Kevin Phone #: ###-#### walls and u/g note need to address show window recepts
|
Electrical Rough-In | 8/15/2011 | 8/16/2011 | 8/16/2011 | A | PASS |
Jack Frank
|
|
|
Inspection needed for underground raceways Phone #: ###-#### >> Inspection requested via web by Kevin Burke ok
|
Rough-In Permanent Service | 8/5/2011 | 8/5/2011 | 8/5/2011 | P | CANC |
Bob Reichert
|
|
|
underground raceway Phone #: ###-#### >> Inspection requested via web by Kevin Burke u/g looked ok from pole to building, told contractor that idaho power u/g is not city work, that city starts at service point, will be more u/g inside building later, service inspection later
|