Final | 10/3/2011 | 10/3/2011 | 10/3/2011 | P | PASS |
Daryl DeGrange
|
|
|
Phone #: ###-#### >> Inspection requested via web by daniel bibikov final ok
|
Electrical Rough-In | 9/16/2011 | 9/16/2011 | 9/16/2011 | P | PASS |
Daryl DeGrange
|
|
|
Heat tile re inspection Phone #: ###-#### >> Inspection requested via web by daniel bibikov corrections made rough-in ok cover floor heat master bath
|
Electrical Rough-In | 9/15/2011 | 9/16/2011 | 9/16/2011 | A | FAIL |
Daryl DeGrange
|
|
|
Heat tile inspection Phone #: ###-#### >> Inspection requested via web by daniel bibikov heat cable not installed to manufactures requirement, need to recess thick portion of cable starter,cable end, cable heat sensor
|
Rough-In Permanent Service | 8/1/2011 | 8/2/2011 | 8/2/2011 | A | PASS |
Daryl DeGrange
|
|
|
Phone #: ###-#### >> Inspection requested via web by daniel bibikov rough-in ok cover service feeders not installed
|
Rough-In Permanent Service | 7/27/2011 | 7/27/2011 | 7/27/2011 | P | FAIL |
Daryl DeGrange
|
|
|
Phone #: ###-#### >> Inspection requested via web by daniel bibikov NEC 225-32 the disconnecting means shall be at a readily accessible location nearest point of entrance of the conductors.
|