Final | 5/1/2012 | 5/2/2012 | 5/2/2012 | A | PASS |
Bob Reichert
|
|
|
Propane tanks in place. Project ready for final. Phone #: ###-#### >> Inspection requested via web by Todd Alder ok final, signed card
|
Final | 4/18/2012 | 4/18/2012 | 4/18/2012 | P | PART |
Jack Frank
|
|
|
Temp occupancy inspection request - Building Dept has temp occupancy permit to sign. Engineer drawings for classified areas onsite. Phone #: ###-#### >> Inspection requested via web by Todd Alder 500.4 documentation ok T/O ok card signed
|
Final | 4/16/2012 | 4/16/2012 | 4/16/2012 | A | NR |
Jack Frank
|
|
|
Inspection for temporary occupancy. Building Dept. has inspection card that needs signed. Phone #: ###-#### >> Inspection requested via web by Todd Alder not raedy called needs too address panel covers, x-former grding see 250.30, also documentationfor classified areas 500.4 and seal all unused KOs
|
Final | 4/4/2012 | 4/5/2012 | 4/5/2012 | P | NR |
Bob Reichert
|
|
|
Building Department has requested an electrical inspection for temp occupancy permit. Building is complete, but compressed gas and propane filling stations located outside building will be completed when occupant moves in. Building Department has requested onsite inspection card be signed for temp occupancy. Phone #: ###-#### >> Inspection requested via web by Todd Alder met contractor, still working on job
|
Electrical Rough-In | 3/13/2012 | 3/14/2012 | 3/14/2012 | P | PASS |
Bob Reichert
|
|
|
Cover inspection for dropped ceiling. Onsite foreman - Shawn Wright ###-####. Phone #: ###-#### >> Inspection requested via web by Todd Alder ok cover ceiling
|
Electrical Rough-In | 2/29/2012 | 2/29/2012 | 2/29/2012 | P | PASS |
Jack Frank
|
|
|
Cover inspection for conduits in trench. Depth adjusted under roadway and tank. Shawn onsite - ###-#### Phone #: ###-#### >> Inspection requested via web by Todd Alder ok voilation corrected
|
Electrical Rough-In | 2/27/2012 | 2/28/2012 | 2/28/2012 | P | FAIL |
Bob Reichert
|
|
|
Cover inspection for underground conduit. Onsite - Shawn, ###-####. Phone #: ###-#### >> Inspection requested via web by Todd Alder called, conduit shall have minimum spacing and be 24" deep under tank and drive at west end building
|
Electrical Rough-In | 2/17/2012 | 2/17/2012 | 2/17/2012 | A | FAIL |
Doug A Poedy
|
|
|
Cover inspection for conduit in trench outside. Onsite foreman Matt Miller - ###-#### Phone #: ###-#### >> Inspection requested via web by Todd Alder. Needs to be 18 inches to top of pipe. Told it was ok to dig down farther then backfill leaving open 2 areas.
|
Electrical Rough-In | 2/2/2012 | 2/7/2012 | 2/7/2012 | A | PASS |
Bob Reichert
|
|
|
Rough-in Cover. Onsite foreman - Matt Miller - ###-#### Phone #: ###-#### >> Inspection requested via web by Todd Alder walls only inside ok cover, check on counter sales u/g since already poured, told contractor to provide area classification drawing as needed
|
Electrical Rough-In | 2/2/2012 | 2/6/2012 | 2/2/2012 | A | CANC |
Jack Frank
|
|
|
Rough-in for cover. Matt Miller onsite foreman - ###-#### Phone #: ###-#### >> Inspection requested via web by Todd Alder Inspection cancelled from web by: Todd Alder
|