Final | 1/9/2015 | 1/9/2015 | 1/9/2015 | P | PASS |
Daryl DeGrange
|
|
|
trim-out was completed different Elect. contractor under permit ELE11-01025, inspected and finaled
|
ELE-Aging Inspection | 1/8/2015 | 1/8/2015 | 1/8/2015 | | DONE |
Cevyn Recla
|
|
|
Building is completed, all units are occupied, permit is open, and TDR has stated that he never finished his work. Someone else has completed the electrical work, and owner has rented out with no inspection.
|
ELE-Aging Inspection | 10/9/2014 | 10/9/2014 | 10/10/2014 | | DONE |
Rex Boyles
|
|
|
trimmed out by another contractor as per Theron
|
ELE-Aging Inspection | 7/10/2014 | 7/10/2014 | 7/10/2014 | | DONE |
Rex Boyles
|
|
|
too busy
|
ELE-Aging Inspection | 4/10/2014 | 4/10/2014 | 4/10/2014 | | DONE |
Rex Boyles
|
|
|
spoke with Theron and he says they roughed it in and owner hired someone else to trim or finsh it. I will look for permit for that
|
ELE-Aging Inspection | 1/9/2014 | 1/9/2014 | 1/9/2014 | | DONE |
Rock A. Hudson
|
|
|
Still under construction
|
ELE-Aging Inspection | 10/10/2013 | 10/10/2013 | 10/16/2013 | | DONE |
Rock A. Hudson
|
|
|
Still under construction
|
ELE-Aging Inspection | 7/11/2013 | 7/11/2013 | 7/15/2013 | | DONE |
Rock A. Hudson
|
|
|
still under construction
|
ELE-Aging Inspection | 4/11/2013 | 4/11/2013 | 4/11/2013 | | DONE |
Rock A. Hudson
|
|
|
still under construction
|
Electrical Rough-In | 2/29/2012 | 2/29/2012 | 2/29/2012 | P | PASS |
Daryl DeGrange
|
|
|
Phone #: ###-#### >> Inspection requested via web by Therrin Robertson rough-in ok cover Need 1 in. KO plug in panel
|
Electrical Rough-In | 2/24/2012 | 2/27/2012 | 2/27/2012 | P | FAIL |
Daryl DeGrange
|
|
|
Phone #: ###-#### >> Inspection requested via web by Therrin Robertson corrections not completed
|
Electrical Rough-In | 2/23/2012 | 2/24/2012 | 2/24/2012 | A | FAIL |
Doug A Poedy
|
|
|
(1) Unit ib building #1 Phone #: ###-#### >> Inspection requested via web by Therrin Robertson. NEC 334.80, NEC 334.30, NEC 300.4
|