Final | 11/7/2012 | 11/7/2012 | 11/7/2012 | P | PASS |
Rock A. Hudson
|
|
|
Steve. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy 2000 amp main load test completed by Current Technologies Job # 2012266 Passed Final ok
|
Conference | 11/5/2012 | 11/6/2012 | 11/6/2012 | P | DONE |
Rock A. Hudson
|
|
|
Steve. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy Signed temp occupancy, need drip protection over panels in mechanical room. All other corrections have been improved. Rocky Mountain Electric Job # 2012266, 2000 amp main load test pass
|
Final | 11/2/2012 | 11/2/2012 | 11/2/2012 | P | PART |
Rock A. Hudson
|
|
|
Steve. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy All main floor ok, food prep areas ok, Items needed- 1. Any 480v Y system rated 1000 amps or more shall be tested by certified 3rd party testing company and a copy of compiance shall be on site as well as filed with the city of Boise, 2. Arc flash labelling shall be on all panel boards and disconnects, 3. Show control boxes on outdoor compactors NEMA 3R rated. 4. Refrigeration compressor assembly disconnect shall be located in a readily accessible location, 6' 7' to top of handle.
|
Final | 10/29/2012 | 10/30/2012 | 10/30/2012 | P | NR |
Bob Reichert
|
|
|
Steve. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy met with 327 and 445 along with contractor, shall provide code sized pull boxes, gfci's, clearances about equipment, listed equipment, support raceways, weather proof operators, shall be ready before call for inspection, agreed to do part inspection because of changes and new permit being pulled, fee due
|
Final | 10/19/2012 | 10/22/2012 | 10/22/2012 | A | CANC |
Rock A. Hudson
|
|
|
Steve Phone #: ###-#### >> Inspection requested via web by Sean DeLacy
|
Electrical Rough-In | 10/22/2012 | 10/22/2012 | 10/22/2012 | A | PASS |
Rock A. Hudson
|
|
|
Steve. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy Service area meat and fish ceiling rough in ok cover
|
Electrical Rough-In | 10/19/2012 | 10/19/2012 | 10/19/2012 | P | NR |
Bob Reichert
|
|
|
Steve. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy met contractor, ceiling wires for fixtures not installed, will recall
|
Final | 10/17/2012 | 10/19/2012 | 10/19/2012 | P | CANC |
Rock A. Hudson
|
|
|
Steve. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy Inspection cancelled from web by: Sean DeLacy
|
Electrical Rough-In | 10/12/2012 | 10/12/2012 | 10/12/2012 | P | PASS |
Rock A. Hudson
|
|
|
Steve. Bakery ceiling cover. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy Bakery ceiling rough in ok cover
|
Electrical Rough-In | 10/11/2012 | 10/11/2012 | 10/11/2012 | P | PASS |
Rock A. Hudson
|
|
|
Steve. PM. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy Secondary entry and juice bar ceiling rough in ok cover
|
Electrical Rough-In | 10/3/2012 | 10/4/2012 | 10/4/2012 | A | PASS |
Rock A. Hudson
|
|
|
Steve. Wall cover. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy Mezz. ceiling rough in cover ok
|
Electrical Rough-In | 10/2/2012 | 10/3/2012 | 10/3/2012 | A | NR |
Bob Reichert
|
|
|
Steve. Ceiling Cover. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy shall finish strapping branch circuits in upstairs ceiling
|
Electrical Rough-In | 9/26/2012 | 9/27/2012 | 9/26/2012 | A | PART |
Doug A Poedy
|
|
|
Steve. Wall cover. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy. Marked on prints.
|
Electrical Rough-In | 9/24/2012 | 9/25/2012 | 9/25/2012 | A | PASS |
Rock A. Hudson
|
|
|
Steve. Service meat department. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy Meat fish ceiling ok cover
|
Permanent Service | 9/13/2012 | 9/14/2012 | 9/14/2012 | A | PASS |
Daryl DeGrange
|
|
|
Steve is on site. Phone #: ###-#### >> Inspection requested via web by Buster Bowen p/s u/g n ok panel borad
|
Electrical Rough-In | 9/11/2012 | 9/11/2012 | 9/11/2012 | P | PASS |
Daryl DeGrange
|
|
|
Steve is on site. Ceiling cover for Mezz Phone #: ###-#### >> Inspection requested via web by Buster Bowen rough-in ok cover mezzanine hard lid
|
Electrical Rough-In | 9/7/2012 | 9/7/2012 | 9/7/2012 | A | PASS |
Daryl DeGrange
|
|
|
Steve. Ceiling Cover. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy rough-in ok cover hard lid Bakerey' Deli
|
Electrical Rough-In | 8/30/2012 | 8/31/2012 | 8/31/2012 | A | PASS |
Daryl DeGrange
|
|
|
Steve. Bakery wall cover. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy rough-in ok cover Bakery walls & meat,fish walls
|
Conference | 8/20/2012 | 8/21/2012 | 8/21/2012 | A | PASS |
Daryl DeGrange
|
|
|
Steve. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy Discuss service grounding and bonding
|
Electrical Rough-In | 8/20/2012 | 8/20/2012 | 8/20/2012 | A | PASS |
Daryl DeGrange
|
|
|
Steve. Wall cover. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy rough-in ok cover 2nd floor westside of hallway up to bathrooms, walls only
|
Electrical Rough-In | 8/13/2012 | 8/14/2012 | 8/14/2012 | A | PASS |
Daryl DeGrange
|
|
|
wall cover for the west exterior wall and the north half of the mezzanine. Steve is the contact Phone #: ###-#### >> Inspection requested via web by Buster Bowen rough-in ok cover
|
Electrical Rough-In | 8/7/2012 | 8/8/2012 | 8/8/2012 | A | PASS |
Daryl DeGrange
|
|
|
Steve. Underground. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy rough-in ok cover remainder of concrete slab
|
Electrical Rough-In | 8/6/2012 | 8/6/2012 | 8/6/2012 | A | PART |
Daryl DeGrange
|
|
|
Steve. Underground. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy rough-in ok cover walker duct as per marked and dated on plans
|
Electrical Rough-In | 8/2/2012 | 8/2/2012 | 8/2/2012 | A | PART |
Bob Reichert
|
|
|
Steve. Underground. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy u/g ok anop
|
Electrical Rough-In | 7/30/2012 | 7/30/2012 | 7/30/2012 | P | PASS |
Daryl DeGrange
|
|
|
STEVE. UNDERGROUND. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy rough-in ok cover underground, back of building #30 Bakery #31 corner area between
|
Electrical Rough-In | 7/18/2012 | 7/18/2012 | 7/18/2012 | P | PASS |
Daryl DeGrange
|
|
|
Steve. Underground. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy rough-in ok cover underground branch circuit conduits from bakery panel
|
Electrical Rough-In | 7/10/2012 | 7/11/2012 | 7/11/2012 | A | PASS |
Daryl DeGrange
|
|
|
Steve. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy rough-in ok cover interior underground service conduits
|
Final | 7/9/2012 | 7/10/2012 | 7/10/2012 | P | CANC |
Bob Reichert
|
|
|
Toby Phone #: ###-#### >> Inspection requested via web by Sean DeLacy wrong permit and request, called, they will recall
|
Electrical Rough-In | 7/3/2012 | 7/5/2012 | 7/5/2012 | A | PASS |
Daryl DeGrange
|
|
|
Steve. Underground. Phone #: ###-#### >> Inspection requested via web by Sean DeLacy rough-in ok cover interror underground (slab)
|