Final | 6/21/2013 | 6/24/2013 | 6/24/2013 | A | PASS |
Daryl DeGrange
|
|
|
early am//Max Phone #: ###-#### final ok
|
Electrical Rough-In | 5/9/2013 | 5/10/2013 | 5/10/2013 | A | PASS |
Rock A. Hudson
|
|
|
MAX Phone #: ###-#### Front entry case work rough in ok cover
|
Electrical Rough-In | 4/24/2013 | 4/24/2013 | 4/24/2013 | P | PASS |
Daryl DeGrange
|
|
|
max Phone #: ###-#### rough-in ok cover remainder ceiling grid
|
Electrical Rough-In | 4/16/2013 | 4/16/2013 | 4/16/2013 | P | PASS |
Daryl DeGrange
|
|
|
max Phone #: ###-#### Rough-in ok cover ceiling grid eat third and 2 high bays area
|
Electrical Rough-In | 4/4/2013 | 4/4/2013 | 4/4/2013 | P | PASS |
Daryl DeGrange
|
|
|
Underground -Max Phone #: ###-#### rough-in ok cover 5 24 in. dia pole base
|
Electrical Rough-In | 3/25/2013 | 3/25/2013 | 3/25/2013 | P | PASS |
Daryl DeGrange
|
|
|
ceiling r/i -- Max Phone #: ###-#### r/i ok cover hard lid entry and waiting area
|
Permanent Service | 3/14/2013 | 3/14/2013 | 3/14/2013 | P | PASS |
Daryl DeGrange
|
|
|
max Phone #: ###-#### p/s u/g n ok
|
Electrical Rough-In | 3/7/2013 | 3/8/2013 | 3/8/2013 | A | PASS |
Daryl DeGrange
|
|
|
Max Phone #: ###-#### rough-in ok cover parking lot underground conduits for parking lot lighting
|
Electrical Rough-In | 2/26/2013 | 2/26/2013 | 2/26/2013 | P | PASS |
Daryl DeGrange
|
|
|
Max Phone #: ###-#### rough-in ok cover walls -north half as per marked and dated on plans
|
Electrical Rough-In | 2/19/2013 | 2/19/2013 | 2/19/2013 | P | PASS |
Daryl DeGrange
|
|
|
Max Phone #: ###-#### rough-in ok cover walls from south end to devising wall
|
Electrical Rough-In | 2/12/2013 | 2/13/2013 | 2/13/2013 | A | PASS |
Daryl DeGrange
|
|
|
Max Phone #: ###-#### rough-in ok cover exterior ceiling southeast mandoor, one recessed luminaire
|
Electrical Rough-In | 2/7/2013 | 2/8/2013 | 2/8/2013 | A | PASS |
Daryl DeGrange
|
|
|
Max Phone #: ###-#### rough-in ok cover walls as per pink highlight and dated
|
Electrical Rough-In | 11/30/2012 | 12/3/2012 | 12/3/2012 | A | PASS |
Daryl DeGrange
|
|
|
max if possible later in the am Phone #: ###-#### rough-in ok cover trench 4in.Data stub
|
Electrical Rough-In | 11/29/2012 | 11/30/2012 | 11/30/2012 | P | PASS |
Daryl DeGrange
|
|
|
MAX Phone #: ###-#### rough-in ok cover floor box in concrete northend floorbox
|
Electrical Rough-In | 11/27/2012 | 11/28/2012 | 11/28/2012 | A | PASS |
Daryl DeGrange
|
|
|
ug r/i--Max Phone #: ###-#### rough-in ok cover trench from temp.service to job trailor location
|
Electrical Rough-In | 11/26/2012 | 11/26/2012 | 11/26/2012 | P | PASS |
Daryl DeGrange
|
|
|
max Phone #: ###-#### rough-in ok cover patient care area underground as per marked & dated on plans
|
Electrical Rough-In | 11/20/2012 | 11/21/2012 | 11/21/2012 | A | PASS |
Daryl DeGrange
|
|
|
early as poss//Max Phone #: ###-#### rough-in ok cover UL listed floor box
|
Electrical Rough-In | 11/16/2012 | 11/16/2012 | 11/16/2012 | P | PASS |
Daryl DeGrange
|
|
|
max Phone #: ###-#### rough-in ok cover conduits under slab as per dated on plan
|
Electrical Rough-In | 11/14/2012 | 11/14/2012 | 11/14/2012 | P | PASS |
Daryl DeGrange
|
|
|
Max Phone #: ###-#### rough-in ok cover underground landscaping conduits as per marked and dated on plans
|
Electrical Rough-In | 11/13/2012 | 11/13/2012 | 11/13/2012 | P | PASS |
Daryl DeGrange
|
|
|
ug//Max Phone #: ###-#### rough-in ok cover underground conduits under slab as per marked and dated on plans
|
Electrical Rough-In | 11/8/2012 | 11/9/2012 | 11/9/2012 | P | PASS |
Daryl DeGrange
|
|
|
ug ri -- Max Phone #: ###-#### rough-in ok cover concrete encased electrode
|