Final | 1/5/2013 | 1/7/2013 | 1/7/2013 | A | PASS |
Rock A. Hudson
|
|
|
code 10020 Phone #: ###-#### >> Inspection requested via web by Bob Glenn Final ok
|
Electrical Rough-In | 12/17/2012 | 12/17/2012 | 12/17/2012 | P | PASS |
Rock A. Hudson
|
|
|
RE INSPECTION ON THE WARM FLOOR Phone #: ###-#### >> Inspection requested via web by Bob Glenn Floor heat rough in ok cover
|
Electrical Rough-In | 12/14/2012 | 12/17/2012 | 12/17/2012 | A | FAIL |
Rock A. Hudson
|
|
|
tHIS IS FOR THE WARM FLOOR IN THE MASTER BATHROOM. THANKS BILL Phone #: ###-#### >> Inspection requested via web by Bob Glenn Floor heat not installed to manufacturers specs. Strapping needed throughout installation, 180 degree turns, factory splice, sensor wire.
|
Rough-In Permanent Service | 11/14/2012 | 11/15/2012 | 11/15/2012 | A | PASS |
Daryl DeGrange
|
|
|
Phone #: ###-#### >> Inspection requested via web by Bob Glenn rough-in p/s u/g n ok
|